Transend - Appendix 5 Renewal capital expenditure - Australian ...
Transend - Appendix 5 Renewal capital expenditure - Australian ...
Transend - Appendix 5 Renewal capital expenditure - Australian ...
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
0BInvestment Evaluation Summary<br />
TNM-GS-809-0720<br />
The YTS relay was installed in 2007. Issues associated this type of relay are discussed above. The Siemens 7SD511 is a<br />
microprocessor based relay that utilises digital differential communications and was installed in 1997. This type of relay<br />
has nine recorded defects over the past five years and there are currently 38 relays installed throughout the transmission<br />
network.<br />
The Siemens 7SD511 is a microprocessor based relay that utilises digital differential communications and was installed<br />
in 1997. This type of relay has 9 recorded defects over the past 5 years and there are currently 38 installed around the<br />
state with 8 spares that have been used in previous installations. These relays will be retained as spares.<br />
Chapel Street–Creek Road–Risdon 110 kV transmission line protection scheme<br />
The transmission line protection on the Chapel Street–Creek Road–Risdon 110 kV transmission line comprises a GEC<br />
type YTS static distance protection relay and an Areva P543 microprocessor relay.<br />
The YTS relay was installed in 2007. Issues associated this type of relay are discussed above. The Areva P543 relay was<br />
temporarily installed in 2006 as part of a transmission line configuration and augmentation project. This relay will be reinstalled<br />
elsewhere in the transmission network or retained as spares.<br />
110 kV bus bar protection<br />
The 110kV bus bar protection installed at Creek Road Substation is a GEC MBCZ low impedance scheme of a static<br />
design that was installed in 1996. This type of scheme has 17 recorded failures over the past five years and there are<br />
currently nine schemes of this type installed throughout the transmission network. Spares are no longer available for this<br />
type of bus bar protection. This type of bus bar protection is not suitable for the revised bus bar configuration and as such<br />
will be retained for spare parts.<br />
4.10 NETWORK DEVELOPMENT CONSIDERATIONS<br />
The 110 kV switchyard at Creek Road Substation is configured as a ring bus arrangement. This arrangement presents<br />
reliability and operational issues, including:<br />
� all transmission circuits and loads are connected to single points on the 110 kV bus bar;<br />
� reduced operational flexibility. Removal of critical plant from service for maintenance purposes requires extensive<br />
planning and transmission network reconfiguration. Loads cannot be transferred to different points on the bus bar,<br />
which constrains plant outages times to summer months (as plant not being maintained is also required to be out of<br />
service). and<br />
� the ring bus arrangement does not readily facilitate extension for future development projects.<br />
Redevelopment of Creek Road Substation 110 kV will enable reconfiguration of the switchyard arrangement to provide<br />
improved reliability and operational flexibility. Each transmission circuit and load will have the ability to connect to<br />
multiple points on the 110 kV bus bar, which will enable all major items of plant to be maintained with minimal<br />
reduction in security of electricity supply.<br />
In 2006, the 110 kV transmission lines between Chapel Street and Risdon substations were augmented to provide<br />
additional capacity to southern Tasmania. The 110 kV transmission network at Creek Road Substation was reconfigured<br />
by removing one 110 kV transmission line connection (and creating a normally-open teed arrangement) to Creek Road<br />
Substation to avoid the need to augment the 110 kV bus bars at Creek Road Substation. This reconfiguration reduced the<br />
security of electricity supply to Creek Substation, albeit whilst providing other benefits. The redevelopment of Creek<br />
Road Substation 110 kV provides the opportunity to install 110 kV bus bars of adequate capacity to optimally configure<br />
the 110 kV transmission network in the vicinity of Creek Road Substation, thereby improving the security of electricity<br />
supply to Creek Road Substation.<br />
5 CUSTOMER CONSULTATION<br />
<strong>Transend</strong> intends to liaise directly with relevant stakeholders regarding the intent, scope and implementation of the<br />
project. The proposed redevelopment project has been highlighted on a number of occasions during <strong>Transend</strong>’s Annual<br />
Planning Review process.<br />
© <strong>Transend</strong> Networks Pty Ltd 9 of 17