This option includes:<br />

� installing new 110 kV GIS;<br />

� new protection and control equipment;<br />

� disposing of existing switchgear and protection and control equipment; and<br />

� demolishing redundant buildings.<br />

The <strong>capital</strong> cost of this option is $26.62 million ($June 2007).<br />

7.5.2 BENEFITS<br />

This option has the following benefits:<br />

� addresses all of the issues in Section 4;<br />

� requires minimal outages for implementation;<br />

� it reduces the ongoing maintenance requirements and costs associated with the site through:<br />

o a reduction in number of circuit breakers;<br />

o a reduction in the number of disconnectors;<br />

o simplification of protection and control schemes;<br />

o rationalisation of infrastructure (post insulators, gantry structures, bus conductors etc.)<br />

� improves the operational flexibility of the site;<br />

� reduces the overall footprint and visual impact of the site;<br />

� allows for some future expansion of the site; and<br />

� allows for rationalisation of auxiliary equipment.<br />

7.5.3 DRAWBACKS<br />

Drawbacks of this option include:<br />

� future expansion costs may be higher than AIS equivalent.<br />

7.5.4 CONCLUSION<br />

This option is technically viable.<br />

7.6 OPTION 6 - REDEVELOP USING HYBRID SWITCHGEAR<br />

7.6.1 SCOPE<br />

0BInvestment Evaluation Summary<br />

TNM-GS-809-0720<br />

This option includes the replacement, rationalisation and reconfiguration of 110 kV assets at Creek Road Substation<br />

using hybrid switchgear. This option includes redeveloping the site using a double bus arrangement as presented in<br />

option 3.<br />

The scope for is the same as option 3, but includes the use of hybrid switchgear in lieu of AIS.<br />

The <strong>capital</strong> cost of this option is $26.62 million ($June 2007).<br />

7.6.2 BENEFITS<br />

� This option has similar benefits to option 3.<br />

© <strong>Transend</strong> Networks Pty Ltd 16 of 17