Transend - Appendix 5 Renewal capital expenditure - Australian ...
Transend - Appendix 5 Renewal capital expenditure - Australian ...
Transend - Appendix 5 Renewal capital expenditure - Australian ...
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
7.6.3 DRAWBACKS<br />
The drawbacks for this option are that:<br />
0BInvestment Evaluation Summary<br />
TNM-GS-809-0720<br />
� it may require longer outages for implementation, depending on the implementation methodology adopted; and<br />
� technology risk as <strong>Transend</strong> has not previously utilised hybrid switchgear in its transmission network.<br />
7.6.4 CONCLUSION<br />
This option is technically viable.<br />
8 OPTION ESTIMATES<br />
A comparison of the net present value of options is provided in Table 1.<br />
Table 1 – Comparison of options considered<br />
Option Net present value of costs ($M June 2007)<br />
1 Manage existing assets and defer replacement -12.71<br />
2 Replace assets in-situ -13.63<br />
3 Staged replacement of selected assets in-situ -13.16<br />
4 Redevelop using air insulated switchgear -13.07<br />
5 Redevelop using gas insulated switchgear -12.68<br />
6 Redevelop using hybrid switchgear -12.67<br />
The economic analysis includes the cost impact to customers in the event of a major circuit breaker failure using a<br />
probabilistic approach based on current and forecast load data for each individual transmission circuit connected to<br />
Creek Road Substation.<br />
9 PREFERRED OPTION<br />
Given the constraints and numerous construction methodologies that may be implemented, options 3, 4, 5 and 6 are<br />
acceptable options.<br />
<strong>Transend</strong> intends to issue this project as a design and construct package to achieve the best economic outcome. The<br />
project documentation will leave it open to tenderers to submit arrangements that may include AIS, GIS or hybrid<br />
switchgear solutions. <strong>Transend</strong> completed a very similar redevelopment project at Risdon Substation. This project was<br />
competitively sourced using a ‘design and construct’ contracting framework. The least-cost solution proposed by<br />
tenderers was the application of GIS technology.<br />
© <strong>Transend</strong> Networks Pty Ltd 17 of 17