24.02.2013 Views

Transend - Appendix 5 Renewal capital expenditure - Australian ...

Transend - Appendix 5 Renewal capital expenditure - Australian ...

Transend - Appendix 5 Renewal capital expenditure - Australian ...

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

0BInvestment Evaluation Summary<br />

TNM-GS-809-0720<br />

7.1 OPTION 1: MAINTAIN EXISTING TRANSMISSION LINE PROTECTION SCHEMES<br />

AND DEFER REPLACEMENTS<br />

This option comprises maintaining the existing transmission line protection schemes.<br />

This option would not satisfy the investment needs and compliance issues outlined in Sections 3 and 4 of this paper. In<br />

addition, it would not align with the strategies detailed in the EHV Transmission Line Protection Asset Management plan<br />

(TNM-PL-809-0701) and would not be consistent with good electricity industry practice.<br />

Maintaining the existing transmission line protection schemes presents the significant risk of failures impacting on the<br />

operation of the transmission network.<br />

7.2 OPTION 2: REPLACE TRANSMISSION LINE PROTECTION SCHEMES<br />

This option comprises the replacement of the 220 kV transmission line protection schemes with new protection schemes.<br />

This option would satisfy all of the investment needs and compliance issues outlined in section 4 of this paper and would<br />

provide all of the benefits identified in Section 6.<br />

In addition, this option is consistent with the strategies detailed in the EHV Transmission Line Protection Asset Management<br />

plan (TNM-PL-809-0701) and is consistent with good electricity industry practice.<br />

8 OPTION ESTIMATES<br />

A detailed net present value (NPV) analysis has been undertaken for each of the options considered. The NPV analysis takes<br />

into account initial and future <strong>capital</strong> <strong>expenditure</strong>, ongoing operations and maintenance costs, unserved energy costs and<br />

estimated costs associated with the loss of generation capacity. A summary of the NPV cost analysis for the options<br />

considered is presented in Table 3.<br />

Table 3 – Summary of NPV cost analysis<br />

Option Net present value of costs ($M June 2007)<br />

1 Maintain the existing assets and defer replacement 2.36<br />

2 Replacement of assets 1.83<br />

9 PREFERRED OPTION<br />

Option two is the preferred option because it addresses all of the identified investment drivers and performance issues at the<br />

lowest NPV cost.<br />

The estimated <strong>capital</strong> cost of this option is $2 million ($Dec 2008).<br />

© <strong>Transend</strong> Networks Pty Ltd 7 of 7

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!