24.02.2013 Views

Transend - Appendix 5 Renewal capital expenditure - Australian ...

Transend - Appendix 5 Renewal capital expenditure - Australian ...

Transend - Appendix 5 Renewal capital expenditure - Australian ...

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

0BInvestment Evaluation Summary<br />

TNM-GS-809-0720<br />

The 110 kV bus bar protection scheme at Farrell Substation was found to be generally compliant. However it does not<br />

meet the redundancy requirements specified in clause 5.1.9(d) of the NER.<br />

The replacement and duplication of the 110 kV and 220 kV bus bar protection schemes at Farrell Substation will ensure<br />

that <strong>Transend</strong> complies with the requirements of the NER as identified in Table 2.<br />

Table 2 – Compliance obligations, issues and project objectives<br />

Reference Compliance obligation Substation issue Project objective<br />

NER<br />

Schedule<br />

5.1.9(d)<br />

NER<br />

Schedule<br />

5.1.9(k)<br />

NER<br />

S5.1.2.1(d)<br />

NER<br />

S5.1a.8 (d).<br />

NEMMCO<br />

Operating<br />

Procedure<br />

SO_OP6100<br />

S8.1.3.1<br />

‘If the fault clearance time determined under<br />

clause S5.1.9(e) of a primary protection system<br />

for a two phase to ground short circuit fault is<br />

less than 10 seconds, the primary protection<br />

system must have sufficient redundancy to<br />

ensure that it can clear short circuit faults of any<br />

fault type within the relevant fault clearance time<br />

with any single protection element (including<br />

any communications facility upon which the<br />

protection system depends) out of service.’<br />

‘A primary protection system may clear faults<br />

other than short circuit faults slower than the<br />

relevant fault clearance time, provided that such<br />

faults would be cleared sufficiently promptly to<br />

not adversely impact on power system security<br />

compared with its operation for the<br />

corresponding short circuit fault. ….’<br />

‘The Network Service Provider must ensure that<br />

all protection systems for lines at a voltage above<br />

66 kV, including associated intertripping, are<br />

well maintained so as to be available at all times<br />

other than for short periods (not greater than<br />

eight hours) while the maintenance of a<br />

protection system is being carried out.’<br />

The fault clearance time of a breaker fail<br />

protection system or similar back-up protection<br />

system for a short circuit fault of any fault type<br />

should not exceed the relevant time in column 4<br />

of Table S5.1a.2 for the nominal voltage that<br />

applies at the fault location.<br />

NB. Column 4 of Table S5.1a.2 states that the<br />

allowable maximum fault clearance time of 430<br />

mS for a nominal voltage of more than 100kV<br />

but less than 250kV<br />

“Unless agreed to the contrary, after sixteen<br />

hours from the unplanned outage of one<br />

protection of a duplicated scheme the power<br />

system equipment must be switched out of<br />

service unless the protection scheme has been<br />

repaired or temporary protection installed.”<br />

Stability studies in the protection audit<br />

report have demonstrated that the 220 kV<br />

bus bar protection requires duplicated<br />

high speed protection schemes to prevent<br />

system stability issues if the bus bar<br />

protection scheme is out of service.<br />

Conventional back-up is too slow to<br />

prevent system instability<br />

Should either of the 220 kV or 110 kV<br />

bus bar protection schemes fail, it is<br />

highly unlikely that the scheme would be<br />

restored within the time required to<br />

comply with this obligation<br />

If either the 220 kV or 110 kV bus bar<br />

protection schemes are out of service<br />

then the existing back-up protection<br />

clearance time is greater than the<br />

allowable clearance time stated in Table<br />

S5.1a.2.<br />

This can result in NEMMCO denying<br />

<strong>Transend</strong> outages required to perform<br />

work<br />

Maximum allowable period for an<br />

unplanned outage of one protection of a<br />

duplicated scheme is 16 hours. The<br />

existing protection schemes are<br />

unreliable and are likely to fail.<br />

Ensure reliable<br />

duplicate protection for<br />

220 kV bus bar<br />

protection schemes<br />

Replace the 220 kV and<br />

110 kV bus bar with<br />

new, protection<br />

schemes that have<br />

adequate redundancy<br />

Provision of duplicated<br />

220 kV and 110 kV bus<br />

bar protection will<br />

result in appropriate<br />

back-up protection fault<br />

clearance times. This<br />

will facilitate the<br />

performance of <strong>capital</strong><br />

and maintenance work<br />

Provision of duplicated<br />

220kV and 110 kV bus<br />

bar protection will<br />

minimise risk of any<br />

future unplanned outage<br />

being greater than 16<br />

hours<br />

© <strong>Transend</strong> Networks Pty Ltd 7 of 10

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!