0BInvestment Evaluation Summary<br />

TNM-GS-809-0720<br />

This project comprises the following works at Burnie Substation:<br />

� replacement of five Reyrolle type 110/OS/10 circuit breakers with dead tank circuit breakers that have integral<br />

current transformers;<br />

� replacement of three Sprecher and Schuh type HPFw-311-L circuit breakers with dead tank circuit breakers that<br />

have integral current transformers;<br />

� decommissioning of the existing post type current transformers;<br />

� installation of five three-phase sets of voltage transformers;<br />

� replacement of the Burnie–Emu Bay 110 kV transmission line protection;<br />

� replacement of the Burnie–Hampshire 110 kV transmission line protection;<br />

� replacement of the Sheffield–Burnie No 2 110 kV transmission line protection; and<br />

� replacement of the bus-coupler protection.<br />

Figure 3 provides a summary of the age of the 110 kV assets (by category) at Burnie Substation by asset replacement<br />

cost of (note that the scope of this project excludes replacement of power transformers, post insulators, disconnectors,<br />

selected protection and control systems and shunt capacitors). Figure 3 clearly illustrates that the vast majority of the<br />

assets included in the Burnie Substation 110 kV redevelopment project are well beyond their nominal service lives of 45<br />

years for primary assets and 15 years for secondary assets as defined by Sinclair Knight Merz in its ‘Assessment of<br />

Economic Lives for <strong>Transend</strong> Regulatory Asset Classes’ report prepared in April 2008 provided as attachment 24 of<br />

<strong>Transend</strong>’s revenue proposal. The majority of the primary assets at Burnie Substation will be over 55 years old when<br />

replaced (the circuit breakers will be 62 years old).<br />

Figure 2 - Age and replacement value ($000) of major equipment installed at Burnie Substation<br />

3 PROJECT TIMING<br />

The timing of this project has been co-ordinated with the prioritised 110 kV circuit breaker replacement program and the<br />

overall <strong>capital</strong> works program. This project is currently ranked 28th of all projects in <strong>Transend</strong>’s works prioritisation tool<br />

and 11th of all renewal projects. The project is currently scheduled to commence in 2011 and be completed in 2014.<br />

It is likely that components of this project may need to be implemented prior to the planned commencement of the<br />

project because of the deteriorated condition of certain assets and the fact that additional asset condition issues will most<br />

likely be identified prior to commencement of the project. It should be noted that these works, should they be needed,<br />

will not result in the need for significant rework because the substation is not being reconfigured.<br />

© <strong>Transend</strong> Networks Pty Ltd 4 of 12