Transend - Appendix 5 Renewal capital expenditure - Australian ...
Transend - Appendix 5 Renewal capital expenditure - Australian ...
Transend - Appendix 5 Renewal capital expenditure - Australian ...
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
7.3 OPTION 3 - STAGED REPLACEMENT OF SELECTED ASSETS IN-SITU<br />
7.3.1 SCOPE<br />
0BInvestment Evaluation Summary<br />
TNM-GS-809-0720<br />
The scope for this option is essentially the same as Option 2, but implemented using a staged approach based on<br />
transmission circuit criticality. This option includes:<br />
� initial replacement of the following assets:<br />
@ Sprecher and Schuh Type HPF 110 kV circuit breakers and associated assets (three bays);<br />
@ other assets that have an assigned transmission circuit criticality rating of four or five (five bays); and<br />
@ other assets that present a safety risk, including selected 110 kV current transformers (two three-phase sets); and<br />
� defer replacement of remaining 110 kV assets by up to three years (two bays).<br />
The <strong>capital</strong> cost of this option includes an initial $5.88 million ($June 2007) to replace critical assets and to address<br />
safety issues followed by a deferred <strong>capital</strong> cost of $0.85 million ($June 2007) to replace remaining 110 kV assets three<br />
years later.<br />
7.3.2 BENEFITS<br />
The benefits for this option are that it:<br />
� allows <strong>Transend</strong> to achieve the <strong>capital</strong> <strong>expenditure</strong> objectives in the mid-term;<br />
� addresses the safety issues associated with the 110 kV assets identified in section 4 of this document, in particular<br />
the 110 kV current transformers;<br />
� defers <strong>capital</strong> <strong>expenditure</strong> associated with lower criticality assets for up to 3 years;<br />
� addresses the performance issues identified in section 4 of this document, with the exception of those transmission<br />
circuits that have a criticality less than four; and<br />
� reduces the ongoing maintenance requirements and costs associated with the site.<br />
7.3.3 DRAWBACKS<br />
The drawbacks for this option are that it:<br />
� results in a higher initial <strong>capital</strong> cost than option 1;<br />
� results in a higher overall <strong>capital</strong> cost than option 2, primarily due to contractor remobilisation and increased internal<br />
costs;<br />
� does not align with <strong>Transend</strong>’s policy to utilise dead tank circuit breakers when replacing 110 kV live tank current<br />
transformers and circuit breakers for two 110 kV bays;<br />
� reduced efficiencies in project delivery, in particular co-ordination of works associated with the Avoca Substation<br />
transformer T2 installation project and asset replacement works; and<br />
� will need additional transmission circuit outages to undertake the works.<br />
7.3.4 CONCLUSION<br />
This option is technically viable.<br />
7.4 OPTION 4 - REPLACE SELECTED ASSETS IN NEW SWITCH BAYS<br />
7.4.1 SCOPE<br />
The scope for this option includes:<br />
� replacement of the existing live tank circuit breakers with dead tank units that have integral current transformers.<br />
The implementation methodology for this option includes constructing new transmission circuit bays and relocating<br />
existing bays sequentially to new bays in order to minimise outage durations. It involves the following key stages:<br />
- developing two new switchgear bays and one new bus-coupler bay;<br />
- restringing the last span of the five transmission circuits into the adjacent bays; and<br />
- extending the 110 kV bus bars to facilitate the installation of the bus coupler.<br />
© <strong>Transend</strong> Networks Pty Ltd 10 of 12