Transend - Appendix 5 Renewal capital expenditure - Australian ...
Transend - Appendix 5 Renewal capital expenditure - Australian ...
Transend - Appendix 5 Renewal capital expenditure - Australian ...
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
0BInvestment Evaluation Summary<br />
TNM-GS-809-0720<br />
The issues pertaining to substation protection and control are discussed in EHV Transmission Line Protection Asset<br />
Management Plan (TNM-PL-809-0701).<br />
5 CUSTOMER CONSULTATION<br />
<strong>Transend</strong> will liaise directly with relevant stakeholders regarding the intent, scope and implementation of the project as<br />
part of the project initiation process.<br />
6 BENEFITS<br />
The direct benefits that are achieved through completing the work outlined in the scope of this project are:<br />
� it will contribute to the achievement of the <strong>capital</strong> <strong>expenditure</strong> objectives identified in the Rules;<br />
� provision of a safe, secure and reliable electricity supply to customers connected to Burnie Substation by replacing<br />
obsolete, unreliable assets that are in poor condition;<br />
� life-cycle cost savings due to reduced operations and maintenance requirements;<br />
� reduced burden on spare parts management by using standard equipment; and<br />
� alignment with strategic asset management plans.<br />
7 OPTIONS ANALYSIS<br />
The following options have been considered for the redevelopment of Burnie Substation:<br />
1. maintain existing assets and defer replacement;<br />
2. replace selected assets in-situ;<br />
3. replace selected assets in new switch bays; and<br />
4. completely redevelop Burnie Substation 110 kV.<br />
Other options considered at a high-level, but discounted for the reasons mentioned include:<br />
� greenfield development – this option was clearly not a cost-effective alternative as other solutions can be<br />
implemented within the existing perimeter of Palmerston Substation at a substantially lower cost.<br />
� reconfigure and rationalise the existing 110 kV switchyard – there are no cost-effective alternatives to<br />
reconfigure or rationalise Palmerston Substation 110 kV.<br />
7.1 OPTION 1 - MAINTAIN EXISTING ASSETS AND DEFER REPLACEMENT<br />
7.1.1 SCOPE<br />
The scope for this option includes:<br />
� replacement of assets that present a safety risk, including selected 110 kV current transformers (eight three-phase<br />
sets) in 2014;<br />
� continue existing maintenance practices, albeit accelerated due to the declining condition and ageing of assets;<br />
� repairs and corrective maintenance as required; and<br />
� deferred replacement for up to five years.<br />
The <strong>capital</strong> cost of this option includes an initial $3.36 million ($June 2007) to address safety issues followed by a<br />
deferred <strong>capital</strong> cost of $4.01 million ($June 2007) to replace remaining 110 kV assets five years later.<br />
7.1.2 BENEFITS<br />
The benefits for this option are the deferral of <strong>capital</strong> <strong>expenditure</strong> and that the identified safety issues are addressed.<br />
7.1.3 DRAWBACKS<br />
The drawbacks for this option are that it would:<br />
© <strong>Transend</strong> Networks Pty Ltd 8 of 12