Transend - Appendix 5 Renewal capital expenditure - Australian ...
Transend - Appendix 5 Renewal capital expenditure - Australian ...
Transend - Appendix 5 Renewal capital expenditure - Australian ...
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
� reduced burden on spare parts management by using standard equipment.<br />
7 OPTIONS ANALYSIS<br />
0BInvestment Evaluation Summary<br />
TNM-GS-809-0720<br />
The following options have been considered for the redevelopment of Meadowbank Substation:<br />
1. Manage existing 110 kV assets and defer replacement;<br />
2. Replace selected 110 kV assets; and<br />
3. Replace all 110 kV assets.<br />
Other options considered at a high-level, but discounted for the reasons mentioned include:<br />
� Off-site greenfield development - not considered to be a cost effective alternative as other solutions can be<br />
implemented within the existing perimeter of Meadowbank Substation at a substantially lower cost. This option was<br />
also discounted for the following reasons:<br />
- the terrain surrounding the area is rugged and uneven, which makes it difficult to find a level ground suitable<br />
for a new development within close proximity to the power station and transmission lines; and<br />
- part of the switchyard has been redeveloped in recent years (high voltage switchgear replacement, building<br />
and security fence).<br />
7.1 OPTION 1: MANAGE EXISTING 110 KV ASSETS AND DEFER REPLACEMENT<br />
7.1.1 SCOPE<br />
The scope for this option includes:<br />
� replace assets that present a safety risk, including post insulators, voltage transformers and current transformers;<br />
� continue existing maintenance practices, albeit accelerated due to the declining condition and ageing of assets.<br />
� undertake repairs and corrective maintenance as required.<br />
� defer replacement for up to five years.<br />
The <strong>capital</strong> cost of this option includes an initial $4.51 million ($June 2007) to address safety issues followed by a<br />
deferred <strong>capital</strong> cost of $1.05 million ($June 2007) to replace remaining 110 kV assets five years later.<br />
7.1.2 BENEFITS<br />
The benefit for this option is the deferral of <strong>capital</strong> <strong>expenditure</strong>.<br />
7.1.3 DRAWBACKS<br />
The drawbacks for this option are that it:<br />
� does not allow <strong>Transend</strong> to achieve the <strong>capital</strong> <strong>expenditure</strong> objectives;<br />
� does not address the performance, reliability and design issues associated with circuit breakers and current<br />
transformer identified in section 4;<br />
� does not address the NER compliance issues associated with the Meadowbank–New Norfolk 110 kV transmission<br />
line protection scheme;<br />
� incurs increased ongoing operating <strong>expenditure</strong> due to increased maintenance, condition monitoring requirements<br />
and corrective maintenance requirements;<br />
� is not sustainable given the reliability issues associated with the 110 kV assets, in particular the circuit breakers and<br />
current transformers;<br />
� incurs longer and more frequent outages due to maintenance regimes that are required to maintain the existing<br />
assets; and<br />
� involves an increased risk of loss of supply events at Meadowbank Substation when compared with other options;<br />
� has the potential to cause voltage issues in the southern region of Tasmania; and<br />
� does not align with the recommendations made in respective asset management plans for primary and secondary<br />
equipment.<br />
© <strong>Transend</strong> Networks Pty Ltd 10 of 12