Transend - Appendix 5 Renewal capital expenditure - Australian ...
Transend - Appendix 5 Renewal capital expenditure - Australian ...
Transend - Appendix 5 Renewal capital expenditure - Australian ...
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
4.3 CURRENT TRANSFORMERS<br />
0BInvestment Evaluation Summary<br />
TNM-GS-809-0720<br />
The 110 kV current transformers in service at Meadowbank Substation (nine single phase units) are Laur Knudsen type<br />
A8ZX units that were manufactured in 1963. A number of identical current transformers installed elsewhere in the<br />
transmission system have been identified as having high percentage power factor readings. This type of current<br />
transformer utilises a silica gel breather that requires the transmission circuit to be removed from service for<br />
maintenance. This deficiency impacts adversely on transmission circuit availability.<br />
The Current Transformer Asset Management Plan (TNM-PL-809-0605) recommends that the Laur Knudsen type A8X<br />
current transformers be progressively replaced with current transformers installed with the dead-tank circuit breakers<br />
because they are generally in poor condition and require frequent maintenance in comparison to modern equivalent units.<br />
The current transformers will be 52 years old when decommissioned.<br />
The average preventive maintenance costs associated with 110 kV current transformers at Meadowbank Substation is<br />
$5 500 per three phase set.<br />
4.4 DISCONNECTORS<br />
The 110 kV disconnectors installed at Meadowbank Substation comprise the following types:<br />
� ABB type DBRP - 1 unit (age 12 years);<br />
� Stanger type DR2 - 3 units (average age 46 years); and<br />
� Switchgear Pty Ltd type DBR-4 - 1 unit (age 46 years).<br />
Generally, the ABB, Stanger and Switchgear Pty Ltd disconnectors in service at Meadowbank Substation are in a<br />
serviceable condition. Given that these disconnectors have proven to be reasonably reliable, they will be refurbished and<br />
retained in service at this time.<br />
The average preventive maintenance costs associated with 110 kV disconnectors at Meadowbank Substation is $2 000<br />
per unit.<br />
Details of each disconnector type are provided in the Extra High Voltage Disconnector and Earth Switch Asset<br />
Management Plan (TNM-PL-809-0606).<br />
4.5 POST INSULATORS<br />
The 110 kV post insulators (approximately 45 units) installed at Meadowbank Substation are a multi-piece construction<br />
that comprise individual insulators bolted together to achieve the required voltage rating. The multi-piece design post<br />
insulators are susceptible to mechanical failure in certain operating environments due to moisture freezing within the<br />
post insulator, causing the porcelain components to crack. <strong>Transend</strong> has experienced a significant number of mechanical<br />
and electrical failures of EHV multi-piece post insulators over the past 10 years. The consequences of failure have<br />
included an increased safety risk to personnel working in switchyards, considerable disruption to electricity supply and<br />
the requirement for unplanned outages to facilitate replacement of post insulators.<br />
The post insulator asset management plan (TNM-PL-809-0614) recommends the progressive replacement of all multipiece<br />
post insulators.<br />
4.6 CONTROL BUILDING<br />
The control building at Meadowbank Substation was designed for the secondary and ancillary systems associated with<br />
the 110 kV assets. There is insufficient space available in the control building to facilitate the planned replacement of<br />
secondary and ancillary systems without disrupting the existing equipment. Extending the control building is not feasible<br />
without major 110 kV asset relocations. Due to this constraint, a new switch house was constructed in 2001 for the<br />
22 kV switchgear and associated protection and control systems. This project includes the extension of the 22 kV switch<br />
house be to provide a greenfield area for the planned replacement of secondary and ancillary equipment. Replacing<br />
secondary and ancillary equipment at greenfield locations is common practice for transmission network service providers<br />
and has been adopted by <strong>Transend</strong> for a number of previous projects. This approach has the following advantages:<br />
� the likelihood of interruption to electricity supply is minimised;<br />
© <strong>Transend</strong> Networks Pty Ltd 7 of 12