0BInvestment Evaluation Summary<br />
TNM-GS-809-0720<br />
Figure 2 presents an aerial view of Arthurs Lake Substation and clearly shows its close proximity to Arthurs Lake. The<br />
access road to the public boat ramp can be seen on the right hand side of the image.<br />
Figure 2 – Aerial view of Arthurs Lake Substation<br />
2 PROJECT OVERVIEW<br />
The planned redevelopment of Arthurs Lake Substation primarily includes the replacement of the three single phase<br />
110/6.6 kV supply transformers, 110 kV circuit breaker, current transformers, post insulators and protection and control<br />
equipment. The substation redevelopment will improve the security and reliability of electricity supply by replacing<br />
assets that are in poor condition and susceptible to failure.<br />
This project comprises the following works at Arthurs Lake Substation:<br />
� replacement of the existing 110/6.6 kV single-phase transformers with a three-phase transformer;<br />
� replacement of the transformer oil containment system with a fully compliant system;<br />
� replacement of the Reyrolle type 110/OS/10 circuit breaker;<br />
� decommissioning of the existing post type current transformers;<br />
� replacement of multi-piece post insulators;<br />
� replacement of all 6.6 kV assets (excluding circuit breaker A352);<br />
� replacement of protection and control schemes; and<br />
� upgrade of the switchyard earthing system to address identified earthing issues.<br />
© <strong>Transend</strong> Networks Pty Ltd 4 of 12