0BInvestment Evaluation Summary<br />
TNM-GS-809-0720<br />
7.4 OPTION 4: COMPLETE REDEVELOPMENT OF KNIGHTS ROAD SUBSTATION<br />
110 KV<br />
7.4.1 SCOPE<br />
The scope for this option includes:<br />
� in-situ replacement of the existing live tank circuit breakers with dead tank units with integral current transformers;<br />
� replacement of 110 kV disconnectors in situ;<br />
� replacement of gantry structures;<br />
� replacement of protection and control schemes; and<br />
� implement revised maintenance practices.<br />
The <strong>capital</strong> cost of this option is $8.58 million ($June 2007).<br />
7.4.2 BENEFITS<br />
The benefits for this option are that it:<br />
� would allow <strong>Transend</strong> to achieve the <strong>capital</strong> <strong>expenditure</strong> objectives;<br />
� addresses the asset and safety issues associated with the 110 kV assets identified in section 4, in particular the<br />
110 kV voltage transformers and post insulators;<br />
� addresses other performance, reliability and design issues identified in section 4; and<br />
� reduces the ongoing maintenance requirements and costs associated with the site.<br />
7.4.3 DRAWBACKS<br />
The option has the following drawbacks:<br />
� higher <strong>capital</strong> cost than option 2.<br />
7.4.4 CONCLUSION<br />
This option is technically viable.<br />
8 OPTION ESTIMATES<br />
A comparison of the net present value of options is provided in Table 2.<br />
Table 2 - Comparison of options considered<br />
Option<br />
Net present value of costs ($M June 2007)<br />
1 Manage existing assets and defer replacement -$5.21<br />
2 Replace selected assets in-situ -$4.71<br />
3 Staged replacement of selected assets in-situ -$4.87<br />
4 Complete redevelopment of Knights Road Substation 110 kV -$5.23<br />
© <strong>Transend</strong> Networks Pty Ltd 12 of 13