0BInvestment Evaluation Summary<br />
TNM-GS-809-0720<br />
� addresses the asset and safety issues associated with the 110 kV assets identified in section 4, in particular the<br />
110 kV voltage transformers and post insulators;<br />
� addresses other performance, reliability and design issues identified in section 4;<br />
� addresses the NER compliance issues associated with the Meadowbank–New Norfolk 110 kV transmission line<br />
protection scheme;<br />
� enables reduced outage duration and ease of implementation (refer to <strong>Appendix</strong> A for proposed implementation<br />
sequence); and<br />
� reduces the ongoing maintenance requirements and costs associated with the site.<br />
7.3.3 DRAWBACKS<br />
The option has the following drawbacks:<br />
� higher <strong>capital</strong> cost than option 2.<br />
7.3.4 CONCLUSION<br />
This option is technically viable.<br />
8 OPTION ESTIMATES<br />
A comparison of the net present value of options is provided in Table 1.<br />
Table 1 - Comparison of options considered<br />
Option Net present value of costs ($M June 2007)<br />
1 Manage existing 110 kV assets and defer replacement -$2.84<br />
2 Replace selected 110 kV assets in-situ -$2.65<br />
3 Replace all 110 kV assets in-situ -$3.37<br />
The economic analysis includes the cost impact to customers in the event of a major circuit breaker failure using a<br />
probabilistic approach based on current and forecast load data for each individual transmission circuit connected to<br />
Meadowbank Substation 110 kV.<br />
9 PREFERRED OPTION<br />
Option 2 (replacement of selected 110 kV assets) is the preferred option because it is the most cost effective solution to<br />
address the identified safety, reliability, condition and design issues at Meadowbank Substation. This approach will also<br />
minimise the number and duration of transmission circuit outages due to reduced frequency and duration of maintenance.<br />
© <strong>Transend</strong> Networks Pty Ltd 12 of 12