26.03.2013 Views

Civil Engineering Project Management (4th Edition)

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

8.3 A note on alternative provisions of the<br />

ECC conditions<br />

The employer and his engineer 91<br />

Under the ECC conditions a project manager is appointed to administer the<br />

contract and he has no duty to act independently or impartially. 1 He represents<br />

the employer, so acts for the employer who is committed by his manager’s<br />

decisions. Consequently the employer has no right under the contract to take<br />

a dispute with his manager to adjudication or arbitration. But if the contractor<br />

disputes any action of the project manager, this comprises a dispute between the<br />

contractor and the employer which can be taken to adjudication or arbitration.<br />

A supervisor on site (with assistants if need be) is also appointed to carry out<br />

certain specified duties relating only to the quality of construction. He inspects<br />

and tests the work (Clauses 40 and 41) and instructs the contractor to search for<br />

and remedy defects (Clauses 42 and 43). He submits reports to the project manager<br />

and the contractor. Where his appointment is separate from that of the<br />

project manager, their respective responsibilities need to be carefully defined<br />

and co-ordinated.<br />

The project manager’s duties include many similar to those listed above<br />

for the engineer under the ICE conditions, in particular under the ECC these<br />

include:<br />

• giving early warning of changes (Clause 16);<br />

• resolving ambiguities in the documents (Clause 17);<br />

• deciding and certifying completion (Clause 30);<br />

• accepting or not accepting the contractor’s programme (Clause 31);<br />

• instructing a suspension of work (Clause 34);<br />

• certifying take over of the works (Clause 35);<br />

• assessing and certifying payments due (Clauses 50 and 51);<br />

• deciding on compensation events, asking for quotations from the contractor<br />

for these and assessing any payment or time extension due (Clauses 60–65).<br />

Further differences between the ECC conditions and ICE conditions are dealt<br />

with in Sections 17.3, 17.8, 17.11 and 17.12.<br />

8.4 Limitations to the engineer’s powers under<br />

ICE conditions<br />

Under the ICE conditions the engineer can only instruct a variation of the<br />

works which is ‘in his opinion necessary for the completion of the works’, or<br />

‘desirable for the completion and/or improved functioning of the works’.<br />

Thus the engineer cannot order matters which are, for instance, extraneous to<br />

1 Although he has no duty to act impartially, he will in practice do so, to avoid a dispute arising which<br />

the contractor takes to adjudication or arbitration.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!