26.03.2013 Views

Civil Engineering Project Management (4th Edition)

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

34 <strong>Civil</strong> <strong>Engineering</strong> <strong>Project</strong> <strong>Management</strong><br />

for the employer since he can gain an income earlier from the project output.<br />

Early completion also suits the contractor, since his overheads extend over<br />

less time and his profit on the job thereby increases.<br />

The problem with bonuses is that, if unforeseen conditions occur causing<br />

the contractor a delay not of his own making, there may be a dispute about<br />

how much extra time should be allowed to him. Bonuses should therefore be<br />

a reasonable amount; not so large that they put the contractor on a win or lose<br />

situation in respect of his whole profit.<br />

(d) ‘Ex-contractual’ payments<br />

These are payments made by an employer to a contractor which are not<br />

authorized by the contract. They are occasionally paid when a contractor has<br />

performed very much to the satisfaction of the employer but has shouldered<br />

some extra cost clearly not attributable to his own actions, such as exceptionally<br />

bad weather or some other misfortune outside his control. Only the<br />

employer can decide to make an ex-contractual payment, not the engineer or<br />

other person acting on his behalf; and the employer must himself have power<br />

to make the payment. Hence a private person or company may be able to<br />

make an ex-contractual payment; but a public authority will usually have no<br />

such power.<br />

(e) Pre-payments<br />

An employer will rarely make an unconditional pre-payment, that is, a down<br />

payment to a contractor at the start of the contract. He can, however, make early<br />

payment to the contractor for provision of offices, laboratory, and transport for<br />

the engineer’s staff on site, etc. (see Section 15.10). These matters by no means<br />

cover the contractor’s outgoings for his initial set-up, especially when the project<br />

is very large and overseas, so significant advance payments, secured by a<br />

repayment bond, are often allowed.<br />

On the Mangla Dam project in Pakistan the contractor needed to purchase<br />

and bring a vast amount of constructional plant on site. To ease the financial<br />

burden on the contractor, the employer (in effect the government) agreed to<br />

purchase or pay for plant required by the contractor up to a value of 15 per<br />

cent of the contractor’s tender price excluding contingencies. The employer<br />

recovered this expenditure by deducting it in instalments over the first<br />

30 months’ interim payments to the contractor under the contract. In this case<br />

the employer could obtain further security for his down payment by retaining<br />

ownership of the plant until he reimbursed his outlay on the plant.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!