Civil Engineering Project Management (4th Edition)
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
48 <strong>Civil</strong> <strong>Engineering</strong> <strong>Project</strong> <strong>Management</strong><br />
I Mech E/ IEE; MF/1<br />
This is for similar purposes as Model Form A but the terms have been modernized<br />
and improved, with revised and extended liability for defects and provision<br />
for performance tests. The first edition was published in 1988 but further<br />
revisions with amendments have been issued, Revision 4 being issued in 2000.<br />
Among other matters, payment terms have to be decided and details added.<br />
FIDIC 2nd and 3rd <strong>Edition</strong>s: ‘Yellow Book’<br />
These apply to mechanical, electrical, instrument and similar work, the provisions<br />
being similar to I Mech E Form A conditions referred to above. The 3rd<br />
edition is a substantially altered and improved version of the 2nd edition.<br />
Again it is intended for work worldwide so it allows for additions to cover<br />
local needs. Although the new FIDIC form for plant is available this form is<br />
still in use.<br />
I Chem E ‘Red Book’ Conditions<br />
These conditions are primarily intended for process plant paid for on a lump<br />
sum basis, with interim progress payments as agreed. The contractor carries<br />
the main responsibility for design but must comply with any requirements set<br />
out in the contract. He arranges all procurement including any civil, mechanical,<br />
electrical and instrument work, etc. and installs, sets to work, commissions<br />
and tests all plant. Performance tests are required to prove that the effectiveness<br />
of the plant is as specified in the contract. Provisions for dealing with<br />
claims and variations are not extensive; the expectation being that, prior to the<br />
award of contract, the parties will have agreed in detail the specific items of<br />
plant to be provided, so that little change is needed. The project manager is<br />
not fully independent, though required to be impartial in some actions; the<br />
purchaser is bound by the decisions made by his project manager and cannot<br />
dispute them in arbitration. Provision is made for an independent expert to be<br />
called in to decide some technical or valuation matters. Since there is little<br />
allowance for unforeseen constructional problems, the conditions may not<br />
be suitable for major associated civil engineering works.<br />
I Chem E ‘Green Book’ Conditions<br />
These conditions cover a cost-reimbursable contract for the provision of<br />
process plant. They can be used when the process or works have not been<br />
fully defined, so both purchaser and contractor may have design inputs; but