26.03.2013 Views

Civil Engineering Project Management (4th Edition)

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

48 <strong>Civil</strong> <strong>Engineering</strong> <strong>Project</strong> <strong>Management</strong><br />

I Mech E/ IEE; MF/1<br />

This is for similar purposes as Model Form A but the terms have been modernized<br />

and improved, with revised and extended liability for defects and provision<br />

for performance tests. The first edition was published in 1988 but further<br />

revisions with amendments have been issued, Revision 4 being issued in 2000.<br />

Among other matters, payment terms have to be decided and details added.<br />

FIDIC 2nd and 3rd <strong>Edition</strong>s: ‘Yellow Book’<br />

These apply to mechanical, electrical, instrument and similar work, the provisions<br />

being similar to I Mech E Form A conditions referred to above. The 3rd<br />

edition is a substantially altered and improved version of the 2nd edition.<br />

Again it is intended for work worldwide so it allows for additions to cover<br />

local needs. Although the new FIDIC form for plant is available this form is<br />

still in use.<br />

I Chem E ‘Red Book’ Conditions<br />

These conditions are primarily intended for process plant paid for on a lump<br />

sum basis, with interim progress payments as agreed. The contractor carries<br />

the main responsibility for design but must comply with any requirements set<br />

out in the contract. He arranges all procurement including any civil, mechanical,<br />

electrical and instrument work, etc. and installs, sets to work, commissions<br />

and tests all plant. Performance tests are required to prove that the effectiveness<br />

of the plant is as specified in the contract. Provisions for dealing with<br />

claims and variations are not extensive; the expectation being that, prior to the<br />

award of contract, the parties will have agreed in detail the specific items of<br />

plant to be provided, so that little change is needed. The project manager is<br />

not fully independent, though required to be impartial in some actions; the<br />

purchaser is bound by the decisions made by his project manager and cannot<br />

dispute them in arbitration. Provision is made for an independent expert to be<br />

called in to decide some technical or valuation matters. Since there is little<br />

allowance for unforeseen constructional problems, the conditions may not<br />

be suitable for major associated civil engineering works.<br />

I Chem E ‘Green Book’ Conditions<br />

These conditions cover a cost-reimbursable contract for the provision of<br />

process plant. They can be used when the process or works have not been<br />

fully defined, so both purchaser and contractor may have design inputs; but

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!