26.03.2013 Views

Civil Engineering Project Management (4th Edition)

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

92 <strong>Civil</strong> <strong>Engineering</strong> <strong>Project</strong> <strong>Management</strong><br />

the works or which add entirely new items; these are matters the engineer<br />

must refer to the employer who will need to negotiate with the contractor his<br />

agreement to undertake the addition (see Section 17.3).<br />

Although the engineer is given a wide range of powers, he should not use<br />

them without reference to the parties to the contract, either of whom may wish<br />

to state his view on matters the engineer has to decide. The FIDIC conditions, for<br />

instance (see Section 4.3), specifically call for such consultation by the engineer<br />

as part of the procedure he must adopt before arriving at his decision.<br />

However, if the employer wishes to restrict the engineer’s powers which<br />

would otherwise be exercisable under the contract, the employer must state<br />

in the tender documents the specific powers which the employer reserves for<br />

himself. Both the ICE conditions Clause 2(1)(b), and the FIDIC <strong>4th</strong> edition<br />

conditions require this. But it is unwise for the employer to reserve too many<br />

powers for himself, because this could affect the basis of contract and reduce<br />

the benefit of having an independent engineer. Tenderers might then take a<br />

different attitude towards the contract, since a tenderer may only offer his lowest<br />

price if he is confident that an independent engineer will administer the<br />

contract. Employers should also be aware that prior approving of matters such<br />

as extension of time or claims may restrict their ability to dispute them later.<br />

However an employer may sometimes wish to ensure that he is involved in<br />

decisions likely to cause additional expenditure above some given limit, or<br />

which alter significantly some aspect of the works. In practice, such restrictions<br />

are unlikely to detract from the engineer’s independent position because<br />

the engineer should keep the employer advised of such matters and endeavour<br />

to agree with him what should be done. Most extra costs arise from having<br />

to deal with unforeseen conditions which must necessarily be dealt with,<br />

or from alterations required by the employer himself.<br />

A different situation can arise if it becomes evident that the estimated final<br />

cost of the contract is approaching or likely to exceed the contract sum. In that<br />

case the engineer must forewarn the employer in good time, because an<br />

employer such as a government or local government authority, may have no<br />

authority to spend more than the contract sum, or may need to go through<br />

a lengthy procedure to obtain sanction for any excess expenditure. In these<br />

circumstances the employer may need to step in and negotiate with the contractor<br />

a change to the works required, or perhaps deferment of construction<br />

of part of the works to some later date.<br />

8.5 The engineer’s duty to provide all necessary<br />

drawings to the contractor<br />

Under the ICE conditions the engineer has a duty to provide the contractor<br />

with the drawings and further instructions needed to carry out the works. This<br />

is additional to the tender drawings issued which do not need to show every<br />

detail. The engineer must therefore watch construction progress to ensure any

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!