26.03.2013 Views

Civil Engineering Project Management (4th Edition)

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

234 <strong>Civil</strong> <strong>Engineering</strong> <strong>Project</strong> <strong>Management</strong><br />

natural ground has to be sufficient to mobilize adequate resistance from the soil<br />

against pipe thrust. Where a bend points down, a weight block below the upper<br />

joint is usually necessary, the joint being strapped down to it. Particular care<br />

has to be taken when a bend down is required at the bank of a river or stream.<br />

There may then be very little ground resistance to prevent the bend blowing<br />

off if the joint is the usual push-in type, hence the upper joint of the bend may<br />

require tying back to a suitable thrust block to resist the hydraulic force tending<br />

to push the bend off.<br />

The watertightness test for a pipeline should be prescribed in the specification.<br />

Care must be taken to fill the pipeline slowly to ensure release of all air. The<br />

usual practice is to fill from one end, having all washouts and hydrants open.<br />

The latter are progressively closed along the line when they cease to emit air or<br />

mixed air and water. This may take a considerable time, as air pockets may<br />

get trapped and only slowly disperse. A satisfactory test cannot be achieved if<br />

an air pocket is left in the pipeline. After filling, the pipe should stand under<br />

pressure for 24 h before testing. This permits pipe expansion and absorption<br />

of water by asbestos cement or concrete pipes or by any mortar lining of steel or<br />

iron pipes. Normally pipelines are tested between valves, but on a trunk main<br />

these may be so far apart that temporary stop ends may be needed to test the<br />

pipeline in reasonable lengths. Especial care is needed in testing partly completed<br />

pipelines to ensure they are properly restrained against the high test<br />

pressures.<br />

An experienced pipelaying contractor will know that care in making joints<br />

on a pipeline is rewarded many times over when the pipeline test shows the<br />

line is satisfactory. It is rarely possible to leave joints exposed before testing, so<br />

if a test fails it may take much time and trouble to find the leak causing it. When<br />

finally found it may be as simple as a twisted rubber ring in a push fit joint. It is<br />

not easy to make clean perfect joints in a muddy trench. The contractor can<br />

save himself money if he gives the jointer every facility to make a good joint –<br />

easy access to see the underside of the pipe spigot, buckets of water and plentiful<br />

clean rags to ensure that joint faces and joint ring are scrupulously clean<br />

before the joint is assembled. No grease or jointing compounds should be<br />

permitted other than that which the pipe manufacturer recommends. Welders<br />

also need sufficient room and good lighting to make sure welds are adequate<br />

and should not be expected to weld up badly aligned pipes.<br />

18.9 Handling and jointing large pipes and fittings<br />

All ductile iron or steel pipes and fittings must be handled with proper wide lifting<br />

slings to prevent damage to their sheathing or coating. The use of chains<br />

or wire ropes ‘blocked off’ pipes with pieces of wood should not be permitted<br />

by the resident engineer. Apart from possible damage to the coating, the packing<br />

pieces may slip out when the chain or wire rope slackens and the pipe may<br />

fall. Handling of heavy pipes and fittings must be done with every precaution.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!