26.03.2013 Views

Civil Engineering Project Management (4th Edition)

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

17.10 Delay claims<br />

Variations and claims 217<br />

The handling of delay claims often poses difficulties. Under the ICE conditions<br />

Clause 44, the engineer can give an extension of time for the contract completion<br />

period if the contractor is caused unavoidable delay. The causes of delay<br />

can be numerous, including failure of the employer to give access to the site, or<br />

failure of the engineer to supply drawings as requested, or to approve the contractor’s<br />

proposed methods of construction in reasonable time, etc. But the principal<br />

causes of delay are often variation orders for extra work and the incidence<br />

of unforeseen conditions (i.e. Clause 12 claims). In addition, Clause 44 permits<br />

an extension of the contract period on account of ‘exceptional adverse weather<br />

conditions’. Clause 44 sets out the procedure to be followed which requires the<br />

contractor to give notice of the delay within 28 days of first experiencing the<br />

cause of delay or ‘as soon thereafter as is reasonable’. The contractor has to give<br />

‘full and detailed particulars in justification of the period of extension claimed’.<br />

Although claims for delay are usually based on extra work ordered or caused<br />

by unforeseen conditions, there can be other delays not associated with extra<br />

work, such as when the engineer instructs the contractor to delay starting some<br />

foundation construction because of the need to conduct foundation tests.<br />

Although a delay of some kind can be caused to a contractor’s work, the delay<br />

of itself does not necessarily entitle the contractor to an extension of the contract<br />

period. The latter is a separate issue, which poses two particular difficulties:<br />

• how to estimate the delay to the job as a whole caused by delay on just one<br />

operation (or a group of operations) when several hundred other operations<br />

are required to complete the job;<br />

• how to estimate what extra cost, if any, is caused by the delay, over and<br />

above that which the contractor is paid for the extra work (if any) causing<br />

the delay.<br />

The answer to the first question is illuminated by considering how critical path<br />

programming (mentioned in Section 14.5) would deal with a delay. Under that<br />

programming, if an activity lying on the critical path has its duration extended,<br />

then the delay to the whole job is likely to be equal to the activity delay. But,<br />

if the activity does not lie on the critical path, its increased duration can either<br />

have no effect on the time to complete the whole job, or it may create a new<br />

critical path, which is longer by some amount than the previous critical path.<br />

However, if it is possible to alter the sequence in which activities are undertaken,<br />

a further critical path may emerge which may be no longer than the original one.<br />

The engineer has to consider whether the contractor could reasonably<br />

avoid delay to the whole project by undertaking other work available; hence,<br />

mitigating the delay. Thus if the contract comprises the construction of a single<br />

building for which the ground conditions turn out so unexpectedly bad that<br />

piling of the foundations has to be added, this would justify an extension to<br />

the contract period. The view cannot be taken that construction of the building<br />

could be speeded up to compensate, because this could involve the contractor

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!