26.03.2013 Views

Civil Engineering Project Management (4th Edition)

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

188 <strong>Civil</strong> <strong>Engineering</strong> <strong>Project</strong> <strong>Management</strong><br />

sub-contract. It is true that, under Clause 59(1) the contractor has to have a<br />

‘reasonable objection’ for refusing to employ a nominated sub-contractor, but<br />

this constraint is of little value in practice. There can also be refusal of either<br />

party to accept the other’s terms for payment – although Clause 59(7) of the<br />

ICE Conditions endeavours to protect a nominated sub-contractor by providing<br />

for direct payment to him if the main contractor fails to pay him.<br />

If the contractor or nominated sub-contractor will not enter a contract<br />

between them for any reason, the nomination fails. The engineer then has to<br />

nominate another sub-contractor, or ask the contractor to do the work himself<br />

or find his own sub-contractor. This mixing of responsibilities between the<br />

employer and main contractor for the performance of a nominated subcontractor<br />

leads to frequent disputes. If the nominated sub-contractor fails to<br />

do the work or goes into liquidation, the employer must take action without<br />

delay, since the main contractor has no duty to carry out the work himself<br />

and will claim for any delay in getting it done. Further, if the sub-contractor’s<br />

work proves unsuitable or not fit for its purpose, the main contractor will deny<br />

responsibility (unless he was expressly charged in the terms of the sub-contract<br />

to take such responsibility – which is unlikely) since he had no choice in the<br />

selection of the sub-contractor or the product.<br />

The extensive disputes which have arisen over the years on these matters,<br />

more particularly in building work with its wider use of nominated subcontractors,<br />

has led many engineers to take the view that use of nominated<br />

sub-contractors in civil engineering should be avoided wherever possible.<br />

The problems most often arise from late completion or defective performance<br />

by a nominated sub-contractor which affects the contractor or his other<br />

sub-contractors. A possible way to avoid this is to specify the work in detail,<br />

providing for its payment by measure under appropriate bill items. Or, if specially<br />

skilled or experienced workers are required to do the work, there is no<br />

reason why this cannot be specified by calling for particular craft skills and<br />

requiring evidence of same. Alternatively, if only one firm can provide the special<br />

techniques required, the letting of a separate contract for such work can be<br />

considered. Although the organization of separate contracts has to be efficiently<br />

managed (as described in Section 5.6), the advantage is that the engineer retains<br />

direct control over the specialist’s work and can act to avoid or solve problems<br />

arising from late delivery or defective work. Where a nominated sub-contractor<br />

is to supply only certain items, the employer may be persuaded to order the<br />

materials direct and store them in advance of being needed; or the contractor<br />

may be instructed to order them early and can be paid for offloading and<br />

storing them on site under items provided in the bill of quantities.<br />

15.9 Prime cost items<br />

When a nominated sub-contract is intended but not yet chosen, a prime cost<br />

item can be inserted in the bill of quantities by the engineer to cover the work

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!