26.03.2013 Views

Civil Engineering Project Management (4th Edition)

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

Measurement and bills of quantities 183<br />

contractor a false impression of the nature of the work. It needs to be borne in<br />

mind that sometimes it is the practice to ‘agree bill quantity’ for an item for<br />

payment if there is no obviously large variation from what the drawings show.<br />

Hence quantities should represent a best estimate of what will occur, in order<br />

to be fair to both contractor and employer.<br />

The problem of rock. A problem occurs when billing rock which may be<br />

suspected but whose incidence is not known – as in the case of a long pipeline<br />

where it is impracticable to sink enough borings in advance to discover the<br />

depth and extent of rock everywhere. Sometimes a provisional quantity is put<br />

in for rock, but if the extent of rock is not known, the problem is to decide what<br />

provisional quantity is to be put in the bill? Also how can the tenderer price<br />

such an item when the actual quantity to be encountered is only ‘provisional’.<br />

Instead, it is suggested, a provisional sum should be included in the bill for rock<br />

excavation, and a price for excavating rock should be agreed with the contractor,<br />

if rock is encountered.<br />

However, a consequent problem is that, if rock is encountered, it will almost<br />

certainly delay the work, so the contractor will put in a delay claim. Despite<br />

this, there is much to be said for negotiating a rate when rock is encountered,<br />

because widely different methods – and therefore costs per unit excavated –<br />

will apply according to the nature and direction of bedding of the rock encountered<br />

(see Section 15.7).<br />

Provisional quantities for other matters should likewise only be used with<br />

care. They should relate to something known to be required, the quantity<br />

being a reasonable judgement as to what might be required. This could apply<br />

to such matters as bedding pipes on soft material, or bedding and haunching<br />

pipes in concrete, or fully surrounding pipes in concrete where the actual<br />

extent of such work depends on the site conditions encountered.<br />

15.6 Billing of quantities for building work<br />

Quite complicated buildings often form part of a civil engineering project, for<br />

example power station buildings, pumping stations, stores, administrative<br />

offices or laboratories. The CESMM gives units of measurement for some<br />

common building operations, but the nature of building work is so diverse that,<br />

in practice, many more items than shown in CESMM will be found necessary.<br />

The CESMM will usually be found suitable for billing all work required to<br />

complete the framework, walling, cladding and roofing to buildings, and such<br />

matters as pipework, roads, sewerage, landscaping and fencing. Other building<br />

items primarily cover the interior finishes, carpentry and joinery, and other<br />

miscellaneous matters. These can be measured by some simple method a civil<br />

contractor will understand, since he will have experience of building work as<br />

well as civil engineering. It is not necessary to follow all the details of the standard<br />

method of measuring building work, for example the many ‘extra overs’<br />

listed in that method for brickwork. The preamble to the bills of quantities

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!