26.03.2013 Views

Civil Engineering Project Management (4th Edition)

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

74 <strong>Civil</strong> <strong>Engineering</strong> <strong>Project</strong> <strong>Management</strong><br />

setting up, etc.; another may spread the cost of such items over all his unit rates<br />

entering only a few, relatively small sums in the Preliminaries Bill. Differences<br />

in rates can also arise from different materials or methods used, different appreciation<br />

of risk, and sometimes from simple error.<br />

If the lowest tender appears impracticably low, the employer may agree that<br />

the engineer should interview the tenderer in the hope of elucidating whether<br />

this results from the tenderer’s inexperience, over-optimism, or misunderstanding<br />

of the contract requirements. However, such a meeting can prove uninformative<br />

leaving the problem still open as to whether such a tender should be<br />

accepted. Acceptance of a tender which would put the contractor to a certain<br />

loss can lead to skimped work or the contractor failing to complete the works. To<br />

allow the tenderer to adjust his faulty price would not be permissible for a<br />

public authority but he can be allowed to withdraw his offer. However, a private<br />

employer is not precluded from bargaining with a tenderer to settle an adjusted<br />

price, or to agree upon some other solution such as offering a bonus to make up<br />

the underpriced item if the contractor completes the works early.<br />

The chances of receiving an unrealistically low tender can be minimized by<br />

avoiding open tendering and giving selected pre-qualified tenderers adequate<br />

time to prepare bids. Before tenders are received the engineer can estimate what<br />

a fair bid price should be. However, under fiercely competitive conditions lower<br />

bids may be received; or if there is much work available or the risks imposed<br />

on the contractor are high, bids can come much higher than expected. If a<br />

contractor expects he will meet administrative problems, difficulty in getting<br />

permits, payments, materials, consents, etc. and suffer from indecision or overcomplicated<br />

authorizing systems run by the employer, he will add a premium<br />

to his prices. It must be realized that contractors pay as much attention to the<br />

competence of employers, as employers pay to the competence of contractors.<br />

A further matter to be examined is the effect of a tenderer’s pricing on the<br />

rate of payments to him during construction, that is, on the cash flow. A contractor<br />

may set his rates for early work high, such as rates for excavation and<br />

foundation concrete. Thus these, containing a large element of profit to him,<br />

will provide him with a good inflow of surplus cash at an early stage in the project.<br />

Similarly he may enter high prices in the Preliminaries Bill for early temporary<br />

works, such as provisions of offices, etc. This pricing is of considerable<br />

financial benefit to a contractor, quickly reducing his start-up costs and borrowing<br />

needs; but it is also a dis-benefit to the employer who, often needing<br />

to borrow money to finance the capital expenditure on the project, has to pay<br />

interest thereon. Comparison of the rates of cash flow implied by different tenders<br />

may therefore need to be made to see their different financial effect on the<br />

employer. If the interest on a employer’s borrowings is capitalized, that is, not<br />

paid when due but added to his borrowings, this can magnify the effect of early<br />

cash disbursement on the employer’s costs, increasing the capital cost of the<br />

project to him. A further point is that a contractor who receives early money<br />

leaves the employer at extra risk, because if the contractor gets into financial<br />

difficulties, much of the early money may not have been spent on permanent<br />

works of value to the employer.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!