26.03.2013 Views

Civil Engineering Project Management (4th Edition)

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

success leads to another. By experience and force of his personality he may<br />

pull the job ahead of schedule and complete before the promised time.<br />

14.7 Completion<br />

One of the duties of the engineer is to decide when the works can be considered<br />

complete. Most contracts require that the works are substantially complete<br />

before the engineer can issue his certificate of substantial completion. Unless<br />

the contract has specific requirements to be met, substantial completion does<br />

not require that every last item is finished, but it is generally taken to mean<br />

that most of the works are done and the project can be put to safe and effective<br />

use by the employer. There will no doubt be some items outstanding and<br />

conditions, such as ICE (7th edition), allow for this while requiring that any outstanding<br />

work is completed as soon as practicable during the defects period<br />

or to an agreed timetable. Items left to be finished later would be those which<br />

do not affect operation, such as painting; or may even include minor structures,<br />

such as a gatehouse not essential to use of the works.<br />

A shrewd contractor will be looking to get his certificate of completion as<br />

early as possible and may apply to the engineer as soon as he thinks he has<br />

any chance of it being allowed. Clause 48 of the ICE conditions (7th edition)<br />

allows for such an application which must, however, be accompanied by an<br />

undertaking to finish outstanding work. The engineer must then either issue<br />

a certificate, or state what needs to be done to complete. The resident engineer<br />

must advise the engineer of matters still to be completed and say if he considers<br />

the contractor’s application for completion is too early. Before the engineer<br />

issues his certificate of completion he will need to check with the employer to<br />

ensure that he has staff available to take over completed works.<br />

14.8 Estimating extension of time<br />

Programme and progress charts 175<br />

Failure to complete in time may make the contractor liable to pay liquidated<br />

damages, as specified in the contract, to the employer. Hence at the time a<br />

completion certificate is issued, the engineer must decide whether any extension<br />

of the time for completion is allowable. Extensions of time may have to<br />

be allowed if the contractor is delayed by problems for which the employer is<br />

liable under the contract. These should have been notified as they arose and<br />

considered at the time (see Section 17.10). There may also be sections of the<br />

work which the contract requires to be completed earlier than for the project<br />

as a whole. It is important to note that not all delays will lead to an extension.<br />

Some may not affect the path to completion and others may be matters for<br />

which the contractor is responsible. It is necessary to check with the contract<br />

conditions (such as ICE 7th edition Clause 44) to identify which delays are to<br />

be taken into account, such as ‘exceptional adverse weather conditions’, etc.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!