26.03.2013 Views

Civil Engineering Project Management (4th Edition)

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

concerning a contractor’s claim, nor does he have to make a decision on a<br />

claim, which does not give ‘full and detailed particulars of the amount claimed’<br />

(Clause 53(4) and (6)). However, once the engineer finds some payment due in<br />

respect of a claim he must certify this payment in the next interim payment to<br />

the contractor.<br />

If the engineer decides that some payment is due to a contractor but unreasonably<br />

fails to certify it in the next certificate; or if the employer fails to pay part<br />

or all of an amount certified for payment by the engineer, the employer has to<br />

pay to the contractor ‘interest compounded monthly for each day on which<br />

the payment is overdue or which should have been certified’ (Clause 60(7)). The<br />

same clause provides that should a matter in dispute go to arbitration, and ‘the<br />

arbitrator holds that any sum or additional sum should have been certified by<br />

a particular date’ then interest will be payable on it, starting from 28 days after<br />

the engineer should have certified the sum. The rate stipulated is 2 per cent<br />

above the base lending rate of the bank specified in the Appendix to tender.<br />

It should be noted that this interest is only applicable following a failure by<br />

the employer or the engineer. There is no general provision that interest is due<br />

for any gap in time between the costs being incurred and an amount being<br />

included in a certificate; much less so if any delay is due to a contractor failing<br />

to supply details of his claim.<br />

17.14 Adjudication<br />

Variations and claims 221<br />

The Housing Grants Construction and Regeneration Act, 1996, (see Section 1.6)<br />

introduced for the first time in English Law a requirement that all construction<br />

contracts must include certain terms. These include payment provisions as set<br />

out in Section 1.6 and also provisions to allow either party to take any dispute to<br />

adjudication at any time. Most standard conditions were immediately amended<br />

to comply with the law, but for those, which were not so amended, the provisions<br />

of The Scheme for Construction Contracts Regulations 1998 will apply. The<br />

provisions of the Act apply to all construction works and work associated with<br />

construction in the UK such as architecture, design and surveying. There are<br />

some limited exceptions such as drilling for oil or gas, supply of materials and<br />

erection of machinery as set out in the Act but in effect most construction<br />

contracts and related consultancy agreements will be included.<br />

The provisions of the Act require that should a dispute arise under the contract<br />

then this dispute can be referred to adjudication at any time and appointment<br />

of an adjudicator must follow within 7 days. The adjudicator must act<br />

impartially and is given wide powers to ascertain the facts and the law. He must<br />

reach his decision within 28 days or a longer period if agreed by both parties.<br />

This period is seen by some as too short for major and complex disputes but<br />

appears to have worked well in practice for straightforward matters including<br />

technical issues, simple claims and claims for non payment. While most standard<br />

forms of contract always had similar provisions, the introduction of

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!