26.03.2013 Views

Civil Engineering Project Management (4th Edition)

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

The problem of setting rates for new work or for omitted items, or where<br />

a quantity change of itself justifies a new rate, can sometimes prove difficult. The<br />

principle in these cases is, however, the same – the billed rates act as the predominant<br />

guide when developing varied rates, because they are the basis of<br />

contract. If this principle is departed from, it can be seen that many complications<br />

could arise in setting new rates since, if one bill rate is not adopted because<br />

it appears too high (or low), then either party could maintain the same applied<br />

to other bill rates, and there would be no clear basis for setting new rates.<br />

It should be noted that the phrase ‘Variation Order’ is not used in most<br />

conditions of contract. Variations in the works are instructed (ICE conditions<br />

Clause 51) and valued (Clause 52). A ‘Variation Order’ then results as a record<br />

of the instruction and valuation.<br />

In the United States the term ‘change order’ is used in lieu of variation order.<br />

17.5 Variations proposed by the contractor<br />

Variations and claims 211<br />

The contractor normally has no right to vary the works and the terms of the<br />

contract will specifically preclude this. But he can make suggestions as to how<br />

the work might be varied, for his own benefit or the benefit of the employer or<br />

both. He has no power to adopt his own suggestion; but if, say, he is unable to<br />

purchase an item required but finds an adequate substitute the engineer would<br />

no doubt agree. On occasion a good contractor will point out a change of design<br />

that has advantages, and the engineer should consider this because the knowledge<br />

of the contractor can assist in promoting a sound construction or reduced<br />

cost (see Section 17.1).<br />

Situations can arise where the contractor’s work does not accord with the<br />

stated requirements. This may be by default when materials or equipment have<br />

been ordered and delivered only for it to be discovered that they are not in<br />

compliance with the specification. Or it may be that workmanship is found<br />

unsatisfactory only after some work has been built, such as concrete of too low<br />

a strength having been used in part of the structure. Under the contract the<br />

engineer has no option but to reject the work; but it may be to the advantage of<br />

progressing the works and preventing delay if the engineer discusses with the<br />

employer and contractor the possibility of accepting what has been provided,<br />

but at an adjusted price. Clearly this is not possible if the difference means the<br />

works will be unsafe or not usable for their intended purpose, but the employer<br />

may be able to accept a lower quality finish or the possibility of increased future<br />

maintenance if the cost of the works is reduced.<br />

Any substitutions offered by the contractor should be referred by the resident<br />

engineer to the engineer, who will decide if the employer’s views should<br />

be sought. The employer is entitled to receive what was shown on the drawings<br />

and specified, and not something else. If any such change is to be accepted the<br />

full terms of agreement including price and time effects must be recorded in<br />

writing to avoid later arguments.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!