26.03.2013 Views

Civil Engineering Project Management (4th Edition)

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

Variations and claims 207<br />

reaching a decision on a claim. But irrespective of whether such requirements<br />

exist, the engineer should always report major claims to the employer and allow<br />

both parties to put their views to him.<br />

On very large projects where an ordered variation may incur heavy extra<br />

expenditure, it is advisable that the employer is involved in the issue of any<br />

order which incurs significant extra cost and many contracts stipulate this. On<br />

many such projects, including the Mangla project mentioned in Section 5.6,<br />

the engineer will report any proposed major variation to the employer for his<br />

agreement, with a technical report in justification. Variation orders can then be<br />

issued in two parts: Part I to issue the necessary instructions to the contractor;<br />

Part II to set out the terms of payment once discussed with the contractor. Thus<br />

urgent variations can be sanctioned by the employer and work can proceed.<br />

The employer needs a sufficiently large technical staff available to appraise the<br />

technical issues involved without delay. The advantage to the engineer is that<br />

the technical issues are thoroughly examined and solutions accepted before<br />

commitment to the very large sums which sometimes have to be sanctioned,<br />

and the advantage to the employer is that he is fully aware of the changes needed<br />

and their effect on the final cost.<br />

While variations are normally decided and instructed by the engineer it is<br />

not uncommon for contractors to put forward ideas either to save cost or time.<br />

Indeed this is encouraged by value engineering procedures and can be a useful<br />

way of controlling or reducing the final price. The ICE conditions recognize<br />

the potential of such proposals and allow for sharing of any changes in value<br />

or time between both parties. Any proposals accepted must be instructed by the<br />

engineer before coming into effect.<br />

Although the rest of this chapter mostly refers to the powers of the engineer<br />

under the contract, this must be taken as implying that the resident engineer<br />

must act similarly.<br />

17.2 Payment for increased quantities<br />

Re-measurement types of contract, such as those covered by the ICE 7th edition<br />

(Measurement Version), are let on the basis that the actual amount of work done<br />

is not expected to be exactly the same as that estimated from the contract drawings.<br />

The intention of the contract is that where a change of quantity requires no<br />

different method of working by the contractor and does not delay or disrupt his<br />

work then the billed rates still apply. However, Clause 56(2) of the ICE conditions<br />

recognizes that, if there is a considerable difference between the measured<br />

and billed quantity, the contract allows a review of the rate to ensure that a<br />

proper price is paid. If the engineer is of the opinion that a quantity has changed<br />

so much that ‘any rates or prices (are) rendered unreasonable or inapplicable<br />

in consequence’, then the engineer, after consultation with the contractor, can<br />

increase or decrease such rates or prices. The change in quantity has to be significant<br />

to justify an altered rate.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!