26.03.2013 Views

Civil Engineering Project Management (4th Edition)

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

a tender is in the tenderer’s hands and he does not have to put a price to any of<br />

the items listed by the engineer in the preliminaries bill. He can mark them<br />

‘included’ meaning the cost of meeting the item requirements is included in his<br />

bill rates for the construction items, or he may enter a low figure.<br />

Items added<br />

A tenderer may sometimes add an item which is not in the list set out in the<br />

preliminaries bill. For instance, he might wish to separately price some especially<br />

expensive temporary works equipment, such as steel shuttering. However,<br />

the employer may have laid down in the Instructions to Tenderers that ‘no<br />

items shall be added to the bill of quantities’. The employer can refuse to consider<br />

such a tender; but if it is the lowest tender received the employer may<br />

decide nevertheless to consider it. This depends on the rules under which the<br />

employer himself operates, such as the standing rules of a public authority, or<br />

government regulations. Normally, however, an extra item or two added by a<br />

tenderer in the preliminaries bill would not be taken as invalidating a tender.<br />

Some contracts specifically allow this by writing in the preliminaries bill ‘Other<br />

items added by contractor…’. If a tenderer does add such items they should be<br />

discussed at tender negotiation stage to agree how they should be paid. For<br />

example, payment of a lump sum for steel shuttering might need to be agreed<br />

as a certain percentage on delivery, the balance on completion of its use.<br />

Method-related items<br />

Measurement and bills of quantities 191<br />

The ICE standard method of measurement of 1985 recognized that items of<br />

the foregoing kind could be added by tenderers. It called them ‘methodrelated’<br />

items, though they are not confined to construction methods but<br />

include organizational measures as well. The CESMM, 3rd edition, lists over<br />

forty such matters that a tenderer can add, covering such as – accommodation<br />

(offices, stores, canteen, etc.); services (water, power, site transport, welfare,<br />

etc.); plant and temporary works of many kinds, ‘supervision and labour’,<br />

and also permits a tenderer to add other method-related items not in those<br />

listed. All such method-related items have to be priced as lump sums, defined<br />

as either fixed or time related. If fixed, the lump sum is only payable when<br />

the work itemized is completed. If ‘time-related’ the payments are spread out<br />

over the time taken to achieve completion of the work covered by the item<br />

(see clarification in Section 16.4). Clearly some items, such as supervision, site<br />

transport, welfare, should not be designated as ‘fixed’ as there is no definable<br />

time when they could be said to be completed, other than the end of the contract.<br />

A tenderer has to define exactly what any item added by him covers,<br />

and whether it is fixed or time-related. Figure 15.2 shows some typical<br />

method-related items entered by a tenderer.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!