164 <strong>Civil</strong> <strong>Engineering</strong> <strong>Project</strong> <strong>Management</strong><br />

technical problems encountered and how they were overcome. The report<br />

should concentrate on such matters that, from experience, can form useful<br />

guidance for future designers and those who draw up contracts.<br />

The RE will save himself much later time and trouble if, as soon as any<br />

equipment arrives, he takes charge of the drawings and instruction manuals<br />

for it and asks the manufacturer for two more copies of them or gets them<br />

copied locally. They are of importance to the employer and should be collated<br />

in some orderly fashion.<br />

A file should be made listing the names and addresses of all equipment<br />

suppliers, and of the suppliers of key materials used in the works, such as<br />

ceramic tiles, facing bricks, cladding, etc. The file should give details of what<br />

was supplied and the date it was ordered. A copy of this file should be given<br />

to the employer for whom it will be valuable when it is necessary to repair<br />

or replace items, or if performance problems occur. Instruction manuals and<br />

plant test data, such as performance curves of pumps, turbines and motors,<br />

should all be collected, and two sets of each should be obtained to supply to<br />

the employer.<br />

An essential requirement for works in the UK is production of a Health<br />

and Safety File (see Section 10.4) at completion of the work. This file is to<br />

be handed over to the client to ensure that information is available to him on<br />

any hazards which may affect anyone doing maintenance work or future<br />

construction work. Under the CDM regulations the planning supervisor is<br />

responsible for ensuring that the file is produced but input will be required<br />

from all concerned and it may fall to the RE to ensure that the various contractors<br />

involved produce relevant information at completion of the job.