26.03.2013 Views

Civil Engineering Project Management (4th Edition)

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

if not, to make some deletion to reduce the cost before the contract goes out to<br />

tender. The estimate can also act as a guide when comparing tendered prices.<br />

3.6 <strong>Project</strong> cost control<br />

Payment arrangements, risks and project cost estimating 39<br />

It is during the design stage that measures to keep the cost of a project within<br />

a budget figure are most effective. All possible savings in design need to be<br />

sought, not only because this is manifestly in the interests of the employer,<br />

but because there are sure to be some unforeseen extra costs that need to be offset<br />

by any savings that can be made. Alternative designs of layout or of parts<br />

of the works have often to be studied before the most economic solution is<br />

found; hence completion of all design before starting construction makes a<br />

major contribution to controlling project cost.<br />

The most prolific causes of extra cost are:<br />

• not completing the design of the works in all essentials before the contract<br />

for construction is let;<br />

• not allowing adequate site investigations to take place;<br />

• encountering unforeseen conditions;<br />

• making changes to the works during construction.<br />

The first two listed above can be avoided by taking the appropriate measures.<br />

The third, however, is not avoidable even if the site investigations have been<br />

as reasonably extensive as an experienced engineer would recommend. The<br />

last – changes during construction – can be minimized by ensuring designs are<br />

complete before construction commences, and that the employer takes time to<br />

assure himself that the works as designed are what he wants. But some changes<br />

are unavoidable if, during construction, the employer finds changed economic<br />

conditions, new requirements or more up-to-date plant, or new legislation<br />

forces him to make a change. The designer should keep aware of possible<br />

changes to the employer’s needs and other technical developments, and not so<br />

design the works that possible additions or alterations are precluded or made<br />

unacceptably expensive.<br />

If tenders are received which exceed the budget estimate by so large a sum<br />

that the employer cannot accept any tender, means of reducing the cost may<br />

have to be sought. Generally speaking, down-sizing a part or the whole of<br />

the works is usually not as successful in reducing costs as omitting a part<br />

of the works. Reducing the output of some works or the size of a structure<br />

by 25 per cent, for instance, seldom results in more than 10 per cent saving<br />

in cost, and can make restoration at a later date to the full output or size an<br />

expensive and uneconomic proposition. If the employer can find some part of<br />

the works which can be omitted, this is a more secure way of reducing the<br />

cost of a project, and it should be possible to negotiate such an omission with<br />

the preferred tenderer.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!