Interim monthly payments 205<br />

the contract. If any are applicable, the employer may wish to deduct them<br />

from any payment due to the contractor, otherwise they may be more difficult<br />

to recover later. At completion the engineer will need to re-assess any extension<br />

of time due to the contractor and advise the employer regarding any<br />

damages due. Deduction of damages is not a matter for the engineer to certify,<br />

but for the employer to decide and apply.