26.03.2013 Views

Civil Engineering Project Management (4th Edition)

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

252 <strong>Civil</strong> <strong>Engineering</strong> <strong>Project</strong> <strong>Management</strong><br />

removed before the mortar layer and new concrete is placed. Usually it is the<br />

job of the resident engineer’s inspector to inspect formwork and the cleanliness<br />

of construction joints before permission is given to the contractor to start<br />

concreting. If the contractor runs ‘Quality Assurance’ one of his staff should<br />

act as inspector of formwork, but this does not relieve the resident engineer of<br />

his need to inspect on behalf of the engineer.<br />

In liquid-retaining structures resilient plastic waterstops are usually provided<br />

at contraction joints. Fixing half their width in the stop-end shuttering<br />

to a narrow reinforced concrete wall often leaves a congested space for the<br />

concrete which must therefore be most carefully vibrated in place to ensure<br />

that the waterstop is bedded in sound concrete. If the concrete face of the joint<br />

is to be bitumen painted before the next wall section is built, bitumen must<br />

not get on the waterstop.<br />

Floor joint grooves need cleaning out by water jetting, then surface drying<br />

as much as possible with an air blower before the priming compound supplied<br />

by the manufacturer of the joint filler is applied to the groove faces. It is<br />

essential that this primer is not omitted, and the filler must be pushed down<br />

to the bottom of the groove. Joint grooves are normally filled after the concrete<br />

has been allowed to dry out for 2 or 3 weeks when most shrinkage on drying<br />

should have taken place (see Section 19.11).<br />

Leaks from liquid retaining concrete structures are most likely to occur<br />

from opening up of wall joints due to wall movement, especially at the corners<br />

of rectangular tanks; and puncturing of the floor joint filler under liquid<br />

pressure where the filler has not been solidly filled to the base of the groove.<br />

19.11 Concrete finish problems<br />

The skill required by carpenters to make and erect formwork for concrete is<br />

seldom fully appreciated. The formwork must remain ‘true to line and level’<br />

despite substantial loading from the wet concrete. Column and wall faces<br />

have to be strictly vertical, and beam soffits strictly level, or any departure<br />

will be easily visible by eye. Formwork for concrete which is to remain<br />

exposed to view has to be planned and built as carefully as if it were a permanent<br />

feature of the building. Many methods have been tried to make the<br />

appearance of exposed concrete attractive: but any of them can be ruined by<br />

honeycombing, a bad construction joint, or by subsequent weathering revealing<br />

that one pour of concrete has not been identical with adjacent pours, or<br />

that the amount of vibration used in compacting one panel has been different<br />

from that used in others. If concrete has to remain exposed to public view,<br />

then the resident engineer should endeavour to agree with the contractor<br />

what is the most suitable method for achieving the finish required if the specification<br />

or drawings do not give exact guidance on the matter. The problem<br />

is that if, through lack of detailed attention, a ‘mishap’ on the exposed surface<br />

is revealed when the formwork is struck, it is virtually impossible to rectify it.<br />

Sometimes rendering the whole surface is the only acceptable remedy.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!