26.03.2013 Views

Civil Engineering Project Management (4th Edition)

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

176 <strong>Civil</strong> <strong>Engineering</strong> <strong>Project</strong> <strong>Management</strong><br />

Assessment of extensions of time may have to be made several times during<br />

a long contract and their cumulative effect will have to be assessed at or<br />

near completion. The assessment needs to take account of all known circumstances<br />

at the time, independently of what may happen later. Also the estimate<br />

is unlikely to be precise because of complicating factors, such as delay<br />

periods overlapping. The engineer has to decide whether delays fairly entitle<br />

the contractor to an extension, so it may be that reference only to the contractor’s<br />

programme is insufficient, since other factors need to be taken into<br />

account to produce a fair result. To make this judgment the engineer needs<br />

experience of constructional processes and their limitations.<br />

An early look at a delay with reference to the contractor’s initial programme,<br />

should take into account that this is only a statement of intent and<br />

that the contractor is at liberty to change his programme. Some operations will,<br />

in the nature of events, take longer or shorter to complete than anticipated.<br />

A more realistic approach is to examine the as-built record of construction to see<br />

if – had the delay not occurred – the construction could have been completed<br />

faster, taking into account any changes made by the employer which have<br />

caused delay. The advantage of this approach is that it is based on actual performance<br />

including any mitigating measures that were taken to reduce delay.<br />

A further discussion of assessing delay and evaluating any payment due is<br />

given in Sections 17.10 and 17.11.<br />

14.9 Estimating probable final cost of works<br />

When a construction project is moving towards completion the employer may<br />

ask for an estimate of its probable final cost. To deal with this it is a help if the bill<br />

of quantities for the project is divided into separate bills for separate structures.<br />

This makes it easier to identify where extra costs have arisen and where further<br />

extras can be expected. The following type of analysis may then be adopted:<br />

• An analysis of amounts incurred under variation orders is made, dividing<br />

them out over the separate bills. The analysis should include VOs pending.<br />

If a VO covers many items spread over several bills, it can be allocated<br />

to general contingency money, to save time on too much detailed analysis.<br />

• The page totals in the original priced bill of quantities should be compared<br />

with the latest page totals for interim payments certified to date. Additions<br />

should be made where, by examination, it is thought payment for items on<br />

that page will come to £500 or more than the original page total shown.<br />

Deductions will be made where it is expected a page total will reduce by<br />

£500 or more because of items omitted, or for which payment under a VO<br />

has been substituted. Smaller differences are ignored. The total for each bill<br />

for a separate structure is then derived by adding up the revised page totals.<br />

• The probable final cost outcome of the main construction contract can then<br />

be assessed as shown in Table 14.1.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!