26.03.2013 Views

Civil Engineering Project Management (4th Edition)

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

32 <strong>Civil</strong> <strong>Engineering</strong> <strong>Project</strong> <strong>Management</strong><br />

definition of which costs will be reimbursed and which will not. Examples<br />

of possible wording to achieve this are given in the IChemE ‘Green Book’ conditions<br />

(see Section 4.5), and in the Schedule of Cost Components included<br />

in the ICE ‘<strong>Engineering</strong> and Construction Contract’ (see Section 4.2(f)). Care<br />

must be taken to ensure the wording adopted is clear. For complex works it<br />

may be necessary to carry out a risk assessment to identify potential problems<br />

and allocate the risks to either party.<br />

(e) Target contracts<br />

These are usually cost reimbursement contracts as (d) above, but with an estimated<br />

target cost set for the works cost, and a fixed or percentage fee for<br />

the contractor’s head office overheads and profit. If the contractor’s expenditure<br />

exceeds the target he has to bear a proportion of the excess; if his expenditure is<br />

less than target he receives a proportion of the difference as a bonus. Thus<br />

there is a financial incentive to the contractor to be efficient and save costs.<br />

But setting a fair target price can be difficult, and impossible if the amount<br />

of work to be done is unpredictable. If a target has to be revised, a dispute<br />

may arise between employer and contractor as to what the new target should<br />

be; this defeats the purpose of this type of contract. If the work is reasonably<br />

well defined, then a measurement contract is usually suitable. Consequently a<br />

target price contract is not appropriate for many jobs.<br />

If the initial target is set as a result of competitive tendering, then the<br />

employer may feel some assurance that he is obtaining ‘value for money’. But<br />

if the target is negotiated or later has to be varied, then the employer may feel<br />

that the contractor’s knowledge of his intended methods and costs may<br />

enable him to add a margin in the target estimate to safeguard his position.<br />

This means that it is improbable that the target cost will ever be lower than the<br />

contractor’s privately estimated bottom line price.<br />

(f) Payment under design, build and operate contracts<br />

Arrangements for payment under design, build and operate (DBO) contracts<br />

may be partly direct and partly by income derived from the project operation as<br />

described in Section 2.6(b).<br />

3.2 Other payment provisions<br />

(a) Price variation provisions<br />

In times of inflation it may be advisable to include clauses within the contract<br />

which set out how the contractor is to be reimbursed his extra costs due to any

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!