26.03.2013 Views

Civil Engineering Project Management (4th Edition)

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

200 <strong>Civil</strong> <strong>Engineering</strong> <strong>Project</strong> <strong>Management</strong><br />

or if not, payment will be dependent on whether they are fixed or time-related.<br />

Fixed sums would be paid as mentioned above for ordinary lump sums, but<br />

problems can arise if the item description is imprecise. Thus if the contractor<br />

has added some method-related item for ‘scaffolding’ or ‘site transport’ as a<br />

fixed sum, it has to be further defined to relate to some specific scaffolding or<br />

specific transport; otherwise it is too vague to identify and cannot be paid until<br />

substantial completion.<br />

When method-related sums are time-related they are paid in monthly<br />

instalments, but the proportion paid will depend on when completion of the<br />

relevant task will be reached. Thus if an item is completed when substantial<br />

completion is achieved, and the programmed time for this is 18 months then,<br />

1/18th payment is added at the end of each month. But if it then appears that<br />

substantial completion will not be reached until month 20, the total payment<br />

due at month 7 is 7/20ths. This is irrespective of whether the delay in completion<br />

is due to the contractor’s tardiness or to an authorized extension of the<br />

contract period. The reason for this approach is that method-related items<br />

are defined as covering ‘costs not to be considered as proportional to the<br />

quantities of the other items’. If an extension of the contract period has been<br />

granted, then any claim for extra payment on that account is a separate matter<br />

to be decided by the terms of the contract. The lump sum payable under a<br />

method-related item remains unaltered.<br />

An adjustment item in the form of a lump sum (see Section 15.11) is paid<br />

in the same proportion as the total payment due under other items less retention,<br />

bears to the total contract sum, less the adjustment item. If a percentage<br />

adjustment has been quoted, this is applied to the total amount payable under<br />

bill items and variations. In both cases the retention money is deducted after<br />

adding in the adjustment item.<br />

16.5 Payment for materials on site<br />

The ICE conditions and similar permit payment to be made to cover part<br />

of the cost to the contractor of materials delivered to site but not yet built into<br />

the works. This can ease the contractor’s cash flow situation and is of advantage<br />

to the employer in encouraging early supply of materials so that unexpected<br />

shortages or late deliveries are less likely to hold up progress. In contracts that<br />

contain such a provision, tenderers can be expected to reduce their prices in<br />

anticipation of the expected financial benefit.<br />

Certifying payment for materials on site is left to the discretion of the engineer.<br />

Under ICE conditions Clause 60(2)(b) he has to certify such amounts (if<br />

any) as he may consider proper, not exceeding a percentage of the value as<br />

stated in the contract. In this he may need to act carefully because, even though<br />

material has been delivered to site, it might still remain the property of the<br />

supplier until he has been paid for it by the contractor. If the supplier falls

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!