26.03.2013 Views

Civil Engineering Project Management (4th Edition)

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

Preparing contract documents 55<br />

matters are considered below. For the standard ICE conditions entries will be<br />

required in the appendix to the Form of Tender but for the ECC conditions it<br />

will be necessary to decide which options are to be included as part of the conditions<br />

of contract as well as making appropriate entries in the Contract Data.<br />

The Defects Correction Period must be stated. This is the period during<br />

which the contractor must repair any defects in the works resulting from his<br />

workmanship. The period is usually 52 weeks for major construction but may<br />

be more or less depending on whether there is running plant involved or how<br />

soon defects may become apparent.<br />

A Performance Bond is usually required where the employer feels he needs<br />

financial protection against a contractor failing to complete the works either<br />

due to lack of resources or financial instability. The size of the bond should cover<br />

having to re-tender and any extra costs to complete. The value should thus be<br />

chosen to suit the work but should not generally exceed 10 per cent of the value<br />

of works. Bonds are, however, relatively expensive to supply and thus put up<br />

prices and so may be considered unnecessary if the contractor is substantial,<br />

or part of a large group who can supply a parent company guarantee.<br />

Insurance against third party risks needs to have a value set with reference<br />

to the likely risks of damage. In a rural area this may be small, but works near<br />

a major industrial complex may need a higher level of cover. Normally it is the<br />

contractor who provides insurance cover both for the works and third parties<br />

but sometimes employers prefer to provide these insurances to save costs.<br />

This can lead to problems when the cover provided does not fully represent<br />

the risks which arise.<br />

The Time for Completion of the works should be set at a reasonable period<br />

given a proper level of resources. In many cases there will be a need for sections<br />

of the works to be defined and separate times for completion to be set for<br />

each of these. Sections may be needed if other contractors are to have access to<br />

the site (e.g. for plant installation) or if parts of the works are needed early.<br />

Since the employer will be kept from using his works and may incur other<br />

costs if the contractor fails to complete on time it is usual to set liquidated<br />

damages to compensate him for his loss. These must be calculated as a genuine<br />

pre-estimate of the loss based on the value of the works output and other costs<br />

anticipated.<br />

Most contracts provide that a portion of the money due to a contractor each<br />

month be retained by the employer. This retention has to be set and is usually<br />

a percentage (often 5 per cent) of the value of works certified up to a limit. The<br />

intention is to provide cover for defects and outstanding work but retention<br />

is unpopular with contractors who point out that bonds and money yet to be<br />

certified for payment provide funds should this be necessary.<br />

5.5 Writing specifications<br />

In writing specifications care must be exercised to ensure consistency of requirements<br />

throughout and conformity with what is written in other documents.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!