26.03.2013 Views

Civil Engineering Project Management (4th Edition)

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

36 <strong>Civil</strong> <strong>Engineering</strong> <strong>Project</strong> <strong>Management</strong><br />

Risk 8, failure to get labour, is usually shouldered by the contractor, mainly<br />

because this lies within the ability of the contractor to control, and not the<br />

employer.<br />

Usually any requirement that the contractor should shoulder all or most<br />

risks arises because the employer prefers to have a fixed financial commitment,<br />

or because he has only a limited allocation of funds which he has<br />

no authority to exceed. Some overseas governments will not authorize any<br />

expenditure above the tendered sum. This fixing of the price and placing all<br />

or most of the risks on the contractor can be expected to lead to generally high<br />

prices. Also if unexpected circumstances occur which the contractor has not<br />

allowed for, he may tend to adopt ‘short-cut’ methods which do not produce<br />

the most satisfactory work, or he may be forced to finish the work at a loss.<br />

For complex projects, and perhaps where major cost reimbursement or target<br />

cost projects are envisaged, a formal risk assessment may be necessary in which<br />

a risk register is set up, defining how each risk is to be dealt with and which<br />

party is to carry the liability should the risk occur. In summary this may involve:<br />

• identification of risks likely to arise by discussion between all interested<br />

parties involved;<br />

• analysis of each risk as to likely frequency, severity of impact on cost and<br />

delay, both maximum and minimum;<br />

• identification as to who is best able to manage the risk and/or who should<br />

carry the costs which may arise;<br />

• definition of risks falling on the contractor so that he can include for them<br />

in his prices or insure against them.<br />

The analysis of risks may be accompanied by a mathematical probability<br />

exercise to try to assess the most likely outcome for the employer’s financial<br />

planning purposes. As a general principle, it is usually best not to pass to the<br />

contractor risks which are most difficult to assess as regards likelihood or cost,<br />

since a contractor may then need to increase his price substantially to protect<br />

his position, causing the employer to pay for a risk which may never arise.<br />

3.4 Producing an initial cost-estimate of a project<br />

At an early stage an employer will want to know the probable cost of his<br />

intended project. Usually no realistic figure is possible until a feasibility study<br />

of the project has been completed; before that only an ‘order of magnitude’<br />

figure or ‘budget estimate’ can normally be quoted. Three main methods of<br />

producing this are as follows:<br />

• by reference to the cost of similar projects;<br />

• by sketch layout and component costing;<br />

• by use of cost curves if available.<br />

The first assumes a record is available of the cost of past projects undertaken<br />

by the employer’s engineer, or perhaps costs taken from the technical press.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!