26.03.2013 Views

Civil Engineering Project Management (4th Edition)

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

228 <strong>Civil</strong> <strong>Engineering</strong> <strong>Project</strong> <strong>Management</strong><br />

the last 150–225 mm of excavation, any loose material being either removed by<br />

hand labour or rolled back with a light roller before placing of the base course for<br />

a road or blinding concrete.<br />

The presence of springs in a soft formation material exacerbates formation<br />

finishing problems. Usually the specification will require spring water to be<br />

led away by grips or drains to a pump sump which is continuously dewatered<br />

to prevent softening of the formation. If springs are encountered and have not<br />

been anticipated, or the method of dealing with them is not specified or shown<br />

on the drawings, the resident engineer should report the situation to the engineer.<br />

Special measures are often required to deal with springs to ensure safety<br />

of the structure to be built on a formation containing them.<br />

18.3 Haulage of excavated material<br />

For large open excavations, such as when road cuttings have to be made and the<br />

material tipped to form embankments, or for building an earth dam from open<br />

borrow pit areas, the motorscraper is the most economical machine for excavating,<br />

transporting and placing clays and clay-sand mixes. But the gradients<br />

traversed need to be gentle and the motorscraper cannot pick up hard bands<br />

of material or rock, unless ripping beforehand can break up the material sufficiently.<br />

If hard or rocky material has to be excavated, the face shovel loading to<br />

dump trucks has to be used, the trucks commonly having a capacity of 50–60 t,<br />

sometimes larger. However, neither scrapers nor dump trucks can traverse<br />

public roads.<br />

If the excavated material has to be routed off site via public roads to some<br />

dumping area, the excavated material has to be carted away by tipping lorries<br />

licensed for use on the public highway. Tipping lorries have a lesser capacity<br />

than dump trucks, usually in the range 10–30 t. A factor often having considerable<br />

influence when needing to transport material along public roads, is the<br />

reaction of the local road and public authorities who may object to the extra construction<br />

traffic and mud on the roads. If the local authority has also to give<br />

planning permission for dumping spoil on some given land, such permission<br />

may only be granted subject to restriction on the size of lorries used and their<br />

frequency of passage. This situation cannot be left for tenderers to find out; the<br />

employer has to obtain the necessary permissions and the contract must reproduce<br />

exactly the conditions laid down by the planning or other authority concerned<br />

and require the contractor to conform to them. If the restrictions limit the<br />

size and frequency of tipping lorries, the contractor may be forced to temporarily<br />

stockpile excavated material on site and double handle it in order to conform<br />

to his intended programme for construction and the haulage conditions laid<br />

down. This will raise his costs for excavation.<br />

Assuming there are no planning restrictions, the contractor needs to choose<br />

that combination of excavating plant and haulage vehicles which achieves the<br />

required excavation rate at lowest cost. The face shovel or backhoe output must

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!