Organizational <strong>Performance</strong><br />
7. On Time Construction<br />
Existing Measure: The percent of construction projects being delivered on time<br />
is currently tracked and reported by <strong>CDOT</strong> and included in the Chief Engineer’s<br />
Objectives and the FHWA-<strong>CDOT</strong> stewardship agreement. <strong>CDOT</strong> is moving<br />
towards defining "on time" delivery as occurring when a project is completed<br />
within the period specified in the contract after the pre-construction conference.<br />
Recommendation: Recommended modification to this measure is to assign a<br />
letter grade based on the thresholds below.<br />
A potential alternative for this measure is to base it on information provided in<br />
the Statewide Transportation Improvement Program (STIP). Measuring against<br />
the STIP would enable <strong>CDOT</strong> to assess performance against the public’s<br />
expectations, which are often established by the project timing information<br />
provided in the STIP. Options include using a project’s original completion year,<br />
as first specified in the STIP as the definition of on time; and assessing the degree<br />
to which progress has been made on a project in each year specified in the STIP.<br />
Letter grades are based on the following thresholds for percent of on time<br />
projects:<br />
Grade<br />
Threshold<br />
A 90 – 100<br />
B 80 – 89<br />
C 70 – 79<br />
D 60 – 69<br />
F < 60<br />
Current Value: 72.2%<br />
Value Based on Recommendation:<br />
Owner: Scott McDaniel<br />
C<br />
Required <strong>Data</strong> Item Source Owner<br />
Project identifier for projects completed in previous<br />
quarter<br />
SAP Projects System Module<br />
Completion date for each project SAP Projects System Module TBD<br />
Project completion data specified in the contract after SAP Projects System Module<br />
TBD<br />
the pre-construction period for each project<br />
TBD<br />
Unit of Measure: Grade<br />
3-18 <strong>Cambridge</strong> <strong>Systematics</strong>, Inc.