09.01.2015 Views

Environmental Impact Statement - Sonoma Land Trust

Environmental Impact Statement - Sonoma Land Trust

Environmental Impact Statement - Sonoma Land Trust

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

<strong>Sonoma</strong> <strong>Land</strong> <strong>Trust</strong><br />

Chapter 4. Consultation and Other Requirements<br />

However, forIn addition to potential turbidity and contaminant effects, the action<br />

alternatives could also result in short-term reductions in dissolved oxygen (DO)<br />

due to discharge of low DO water during implementation of Breach 1 (if standing<br />

water remains as a result of pre-vegetation or seasonal precipitation), and/or<br />

reductions in DO due to decay of submerged vegetation following restoration of<br />

tidal action. As discussed in Section 3.3, tidal flushing would quickly restore DO<br />

levels to ambient concentrations. This potential impact would be of short<br />

duration, and would also be localized. Even if other restoration projects where<br />

construction has not yet been completed are breached during the same time frame<br />

as the Sears Point project, there would be no cumulative impacts. Compliance<br />

with permit conditions and implementation of the water quality control measures<br />

identified in Mitigation Measures WQ-MM-1, WQ-MM-2, WQ-MM-43, HAZ-<br />

MM-1, and HAZ-MM-5 would adequately protect against degradation of water<br />

and sediment quality due to release of construction-related pollutants and thus<br />

hazards due to release of such hazardous materials levee breaching and potential<br />

low DO conditions and thus avoid any considerable contribution to cumulative<br />

water quality impacts during construction.<br />

As discussed in Section 3.3, Water Quality, it is currently unknown whether the<br />

effects of the restoration alternatives on methylmercury production would be<br />

more notable than the natural methylation processes. It is generally thought that<br />

restoring large areas of tidal marsh throughout the San Francisco Bay region<br />

would be beneficial to the environment. However, large-scale restoration projects<br />

could expose populations of special-status species to increased concentrations of<br />

methylmercury, if new areas of tidal marsh added over a short period of time<br />

actually resulted in an increase of mercury methylation over existing conditions.<br />

Mitigation Measure WQ-MM-32 requires the implementation of a<br />

methylmercury adaptive management plan based on consultation with the<br />

relevant local, state, and federal agencies. The likely outcome of the adaptive<br />

management plan would be informed decision making that would guide the<br />

phased restoration of tidal marshes throughout the estuary. Depending on the<br />

findings of the subsequent monitoring and other studiesy, it, further adaptive<br />

management actions may be necessary to schedule the amount and timing of<br />

restoration activity to reduce mercury methylation within water bodies adjacent<br />

to multiple wetland restoration projects. However, because it currently remains<br />

unknown whether wetland restoration would actually resultrequired in increased<br />

mercury methylation,the long term, and an adaptive management approach is<br />

appropriate. The contribution of either action alternative to potential cumulative<br />

methyl mercury impacts can be reduced to a less than significant level with<br />

implementation of Mitigation Measures WQ-MM-2.<br />

Apart from With implementation of the methylmercury potential noted above,<br />

the project is notmitigation measures outlined in Section 3.3 and 3.9 neither<br />

action alternative is expected to result in a considerable contribution to a<br />

significant cumulative water quality impact. The contribution of the project to<br />

potential cumulative methyl mercury impacts can be reduced to a less than<br />

considerable level with implementation of Mitigation Measures WQ-MM-3.<br />

Sears Point Wetland and Watershed Restoration<br />

Project Final <strong>Environmental</strong> <strong>Impact</strong><br />

Report/<strong>Environmental</strong> <strong>Impact</strong> <strong>Statement</strong><br />

4-12<br />

April 2012

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!