California Department of Fish and Game<br />

U.S. Fish and Wildlife Service<br />

Chapter 2. Alternatives<br />

Creek Restoration Area. Breaches 3 and 4 would most likely be smaller than<br />

Breaches 1 and 2, and would require less excavation. If Breaches 3 and/or 4 are<br />

required, they would either be constructed once Caltrans has implemented<br />

improvements to protect Highway 37 from flooding at the Upper Lagoon of<br />

Tolay Creek (as a separate and independent project), or would require hardening<br />

a small portion of Tolay Creek just south of the Upper Lagoon to mute the tidal<br />

range reaching Highway 37. In the case of the latter, the narrowest point of the<br />

channel south of the Upper Lagoon in Tolay Creek would be hardened using<br />

riprap, gravel, cobble, articulated mats, or similar armoring. This would require<br />

up to approximately 2,000 CY of material, placed along the side slopes and<br />

bottom of Tolay Creek, and cover a footprint of up to approximately 30,000<br />

square feet.<br />

Constructing all four breaches and the connector channel (see below) could<br />

require removing up to approximately 145,000 CY of material and disturbing a<br />

total of up to approximately 8.7 acres of tidal marsh. Because these small<br />

volumes of excavated materials would be highly saturated and would be difficult<br />

to transport to other areas of the project site, they could be used to construct<br />

Marsh Mounds or side cast inside the site adjacent to the breaches. The typical<br />

equipment used for this work would be an excavator or a long reach excavator. If<br />

material was hauled to other areas of the site for reuse off-road trucks would<br />

likely be used.<br />

Improving tidal exchange in Tolay Creek is no longer a component of the project,<br />

therefore dredging and widening of Tolay Creek has been removed from this<br />

project description.<br />

Dredging<br />

Dredging between the site and Tolay Creek would further enhance hydraulic<br />

connections, allowing for eventual full unimpeded tidal flow in Tolay Creek.<br />

Dredging would be accomplished with a hydraulic rotary cutter head suction<br />

dredge. The dredged materials would be piped into the tidal wetlands area and<br />

used to refill borrow pits or generally raise the interior grade. The dredging<br />

process water would be held in a detention pond and returned to the Bay/Creek in<br />

compliance with water quality permit conditions. In the event that the dredged<br />

material was unneeded or unsuitable for on-site use, this dredging could be done<br />

with a small clamshell dredge and the material could be barged to an open water<br />

disposal area or other suitable reuse option.<br />

Considering the local bathymetry and the size of the project, a 10- to 14-inch<br />

hydraulic dredge would be used. The dredge would be diesel-powered and have<br />

engines totaling about 700 horsepower (hp). A tender tug of about 300 hp and a<br />

crew boat of about 150 hp would also be in use part of the time. On the land side<br />

placement area, a small bulldozer or loader would be used to move the dredged material<br />

pipeline as needed. Temporary drainage pump(s) of approximately 70 hp would<br />

likely be required to return the process water to the Bay/Creek. These pumps<br />

Sears Point Wetland and Watershed Restoration<br />

Project Final <strong>Environmental</strong> <strong>Impact</strong><br />

Report/<strong>Environmental</strong> <strong>Impact</strong> <strong>Statement</strong><br />

2-11<br />

April 2012