WEST AFRICAN POWER POOL (WAPP) PÖYRY ENERGY LTD.<br />

Mount Coffee HPP ESIA and RAP 2012-09-18<br />

ESIA Report Page 183<br />

Table 25-1: MCHPP Rehabilitation, total project cost<br />

Project Name Mount Coffee HPP Via Storage Project Total<br />

Total cost 162 221 383<br />

The costs of the project are expressed in US $ of 2008. They include all the project<br />

components, administration, contingencies, indirect costs, taxes and import duties.<br />

Stanley Consultants estimated that the project could be realized in four and a half years<br />

and proposed the following annual investment requirements, in million US $:<br />

Table 25-2: MCHPP Rehabilitation, annual investment requirements<br />

Project 2008 2009 2010 2011 2012 2013 Total<br />

Mt Coffee 1 30 33 62.5 33.5 2 162<br />

Via 1 22 33 82.5 82.5 0 221<br />

Total 2 52 66 145 116 2 383<br />

25.2.2 Study Options for the Development of Liberia’s Energy Sector<br />

The paper “Options for the Development of Liberia’s Energy Sector” was completed in<br />

October 2011 for the International <strong>Bank</strong> for Reconstruction and Development. Its<br />

purpose was to show options for the supply of electricity to Liberia. Accordingly a<br />

Least-Cost Energy System Expansion for the Period 2010 to 2040 was developed.<br />

For the preparation of this system expansion plan, about a dozen options were studied.<br />

The rehabilitated Mount Coffee Hydropower Plant and a few other hydropower projects<br />

to be located on the St. Paul River formed some of the considered options.<br />

The technical and economical characteristics of the considered hydropower plant<br />

options were taken over from the Stanley Consultants Feasibility Study of 2008 and are:<br />

Table 25-3: Considered HPP options, technical and economic characteristics<br />

Project Name Capacity Energy Capital Cost<br />

MW GWh Million US $<br />

Mount Coffee 66 342 162<br />

Mount Coffee + Via storage 66 435 383<br />

SP-1B +SP-2 + Via storage 198 1’960 879<br />

St Paul-2 (SP-2) project is located on the St Paul River 60 km downstream of the<br />

planned Via Reservoir. It will produce 1’330 GWh. St Paul-1B (SP-1B) will be located<br />

40 km downstream of SP-2 and will produce 630 GWh.<br />

The capital costs shown in the preceding table are expressed in 2008 US $. For the<br />

development of the least cost expansion plan, these costs were updated to the year 2009<br />

and discounted to the year 2010 with a discount rate of 12%.