Temperature - European Investment Bank
Temperature - European Investment Bank
Temperature - European Investment Bank
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
WEST AFRICAN POWER POOL (WAPP) PÖYRY ENERGY LTD.<br />
Mount Coffee HPP ESIA and RAP 2012-09-18<br />
ESIA Report Page 213<br />
All the structures were regularly monitored and well maintained. In the 1980s, these<br />
controls revealed that the condition of the foundations of the dam indicated the<br />
approach of the end of the operating life of this structure. It was therefore necessary to<br />
either remove or replace dam and plant. Extensive studies were then conducted to<br />
carefully assess the various options (technical studies, EIA: EWI 1987). These studies<br />
were designed to identify the best solution, which would then be implemented from<br />
2000 to 2006.<br />
In addition to technical considerations, both economic and financial (cost of<br />
decommissioning work with or without replacement of structures, power generation),<br />
the most important points to consider were environmental issues:<br />
� Landscape: In over 100 years of existence of the reservoir, the surrounding<br />
landscape, including the developed and inhabited zones, had adapted to a "lake"<br />
situation; lowering the water level by about ten metres (and more in the vicinity of<br />
the dam) would cause a significant change in this situation.<br />
� Sediment: thanks to the great lake of Constance and the other reservoirs upstream<br />
of the dam, the amount of sediment that had accumulated in the reservoir was<br />
relatively small and did not in any way affect the continuous operation of the plant.<br />
Nevertheless, the dismantling of the dam without replacement would have meant<br />
mobilizing these sediments. Now, there was a risk that these sediments could<br />
contain unknown amounts of harmful substances, the result of industrial activities<br />
for a period of almost 50 years upstream of the dam. As long as the sediments were<br />
still in place, these substances did not constitute a risk, but mobilising the sediments<br />
would have necessitated preventive measures (excavation and disposal on land of<br />
these substances), which would have been very costly.<br />
The solution adopted in this case, taking into account the considerations described<br />
briefly, involved the construction of a new dam and power plant a hundred metres<br />
downstream of the existing dam, which was then removed. With this solution, energy<br />
production could be maintained and even increased significantly (installed capacity of<br />
the new plant: 100 MW), and the situation in the reservoir area (water level and thus the<br />
landscape, sediment) remained unchanged. The construction started in 2006, and the<br />
new plant was commissioned in 2010.<br />
In the case of Mount Coffee power plant, when the time comes, a similar procedure will<br />
have to be followed, with a detailed analysis of the options. It will certainly be<br />
necessary to carry out technical feasibility studies, and as with the construction, to<br />
prepare an ESIA for the dismantling or replacement of the dam. Just like in the case of<br />
Rheinfelden, the issue of sediments will be something to consider, among others.<br />
According to the available technical studies, sedimentation is not of major concern in<br />
the Mount Coffee reservoir. Depending on the development of the cascade (with the<br />
large Via storage reservoir and additional dams and power plants between it and Mt.<br />
Coffee) sediment input to the latter could still be further reduced. Nevertheless, it is<br />
obvious that over an operation period of 50 to 100 years still a large amount of sediment<br />
will be accumulated in the reservoir, which would be transported downstream should<br />
the dam be removed. This could cause serious problems downstream of the site, e.g. for<br />
the fauna (fish), water use (like drinking water intakes) and the estuary (mangroves).<br />
This will have to be evaluated carefully, taking into account the situation at that<br />
moment.