01.12.2012 Views

Temperature - European Investment Bank

Temperature - European Investment Bank

Temperature - European Investment Bank

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

WEST AFRICAN POWER POOL (WAPP) PÖYRY ENERGY LTD.<br />

Mount Coffee HPP ESIA and RAP 2012-09-18<br />

ESIA Report Page G<br />

required. These mitigation measures are summarised in Chapter 20, while Chapter 21<br />

provides a provisional environmental and social management plan (ESMP). This plan<br />

also outlines organisation and structures required for the implementation of the plan. It<br />

is important to see that the project proponent as well as the contractor(s) will have to<br />

develop their own specific ESMPs, and will need to have the required organisation on<br />

site, since the most sensitive phase it the construction period.<br />

Chapter 22 describes very shortly the resettlement plan; this is work still under way.<br />

Public participation (Chapter 23) is an on-going process, which will go into its next<br />

decisive phase as soon as this report will have been accepted and will be presented to<br />

the affected population.<br />

The next chapters deal with a number of specific projects related issues. Project<br />

alternatives are discussed in Chapter 24. The main alternative to using hydropower<br />

would be to continue and expand the use of fuel oil for producing electricity. This is not<br />

a sustainable solution, neither from an economic (high costs) nor from an environmental<br />

(air pollution, GHG emissions) point of view. Concerning dam site or main dimensions<br />

of the scheme here are no real alternatives to Mt. Coffee HPP as planned; the "no<br />

project" case is not considered as a valid alternative for the country. Alternative<br />

engineering design (e.g. roller compacted concrete instead of an earthfill dam are not of<br />

relevance from an environmental and social point of view. There is a possibility to<br />

increase installed capacity from 66 to 80 MW. This would cause a minor change in<br />

downstream flow conditions (less spilling, since more water would pass through the<br />

turbines); this change would not have any relevant negative impact.<br />

An economic evaluation of the project was also carried out as part of the ESIA (Chapter<br />

25). For this purpose the latest information and reports were collected in Liberia,<br />

documenting the conditions prevailing in the power market of Liberia and the main<br />

features of the Mount Coffee Hydropower Plant Rehabilitation Project. The review of<br />

the collected material showed that Liberia is in an urgent need for electricity. Under<br />

these circumstances and taking into account that the implementation of the Mount<br />

Coffee Hydropower Plant Rehabilitation will take four to five years, one can expect that<br />

within a short period of time the complete production of Mount Coffee Hydropower<br />

Plant can be absorbed by the consumers of Liberia.<br />

The various possible other options to supply the growing need for electricity were<br />

identified and compared. Mount Coffee Hydropower Plant and HFO thermal power<br />

plant turned out to be the most promising options. To perform the economic analysis<br />

updated information (end of February 2012) on the Mount Coffee Hydropower Plant<br />

Rehabilitation Project could be obtained. Especially relevant were the mean annual<br />

energy production and the construction cost. The value of the energy generated by<br />

Mount Coffee Hydropower Plant was taken as equal to the unit cost of electricity<br />

produced by a HFO thermal plant. The economic analysis was performed for the Base<br />

Case with a discount rate of 10% and for various Sensitivity Cases. For the sensitivity<br />

analysis, discount rates of 12% and 8% were used, the construction cost increased by<br />

25% and the fuel cost (HFO) raised also by 25%. For all the cases studied, the Net<br />

Present Value (NPV) was always significantly higher than zero. The Economic Internal<br />

Rate of Return (EIRR) was higher than 17% and the unit cost of the generated<br />

electricity, below 9.5 US cents per kWh.<br />

Under these circumstances Mount Coffee Hydropower Plant Rehabilitation Project is<br />

surely economically a very attractive option for the supply of electricity to the Greater

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!