As a result, the probability distributions for the financial and economic performance indica<strong>to</strong>rs arecalculated using the Monte-Carlo method and specialist s<strong>of</strong>tware. Figure 4.8 shows, as an example, theprobability distribution obtained for the ENPV. In Table 4.34, other characteristic probability parametersare given (in thousands <strong>of</strong> Euros and percentages).Table 4.34 Risk analysis: characteristic probability parameters <strong>of</strong> the performance indica<strong>to</strong>rsFNPV(C)ENPVReference value (base case) -71,877 259,680Mean -74,353 259,842Median -71,920 260,595Standard deviation 26,339 29,640Minimum value -159,475 163,406Maximum value -82,188 360,235Probability <strong>of</strong> the parameters being not higher than the reference value -71,877 259,680Figure 4.7 Probability distribution assumed for the <strong>investment</strong> costPr. distr.Ref. value0,50,450,40,350,30,250,20,150,10,050140 150 160 170 180 190 200 210 220 230 240Incenera<strong>to</strong>r <strong>investment</strong> cost (M€)Figure 4.8 Calculated probability distribution <strong>of</strong> ENPVPunctual probabilityReference valueCentralMeanSD uppCumulated probabilityMi nimumMaximumSD lowMedian1,000,900,800,700,600,500,400,300,200,100,00150.000 170.000 190.000 210.000 230.000 250.000 270.000 290.000 310.000 330.000 350.000ENPV162
Table 4.35 Financial return on <strong>investment</strong> (thousands <strong>of</strong> Euros)1 2 3 4 5 6 7 8 9 10 11 12 13 14 15Municipal waste 0 0 0 1,719 3,489 3,541 3,593 3,647 3,701 3,756 3,812 3,869 3,927 3,985 4,045Other waste 0 0 0 129 262 266 270 274 278 282 286 290 295 299 303Electricity 0 0 0 3,716 7,625 7,824 8,029 8,238 8,454 8,674 8,901 9,134 9,372 9,617 9,868Heat 0 0 0 2,132 4,379 4,498 4,620 4,745 4,874 5,006 5,142 5,282 5,425 5,572 5,724SALES 0 0 0 7,695 15,755 16,128 16,511 16,904 17,307 17,719 18,142 18,575 19,019 19,473 19,940Labour cost 0 0 0 1,859 1,905 1,952 2,001 2,051 2,102 2,154 2,208 2,263 2,319 2,377 2,436Gas 0 0 0 105 216 223 229 237 244 252 259 268 276 285 293Eectrical energy 0 0 0 241 495 510 525 540 556 572 589 606 624 642 660Water services 0 0 0 3 7 7 7 7 8 8 8 8 8 9 9Raw material 0 0 0 141 287 293 299 305 311 317 323 330 336 343 350Intermediate services and goods 0 0 0 703 1,434 1,463 1,492 1,522 1,552 1,584 1,615 1,647 1,680 1,714 1,748Elimination <strong>of</strong> ash and slag waste 0 0 0 1,460 2,978 3,037 3,098 3,160 3,223 3,288 3,353 3,420 3,489 3,559 3,630TOTAL OPERATING <strong>COST</strong>S 0 0 0 4,511 7,322 7,485 7,651 7,821 7,995 8,173 8,355 8,541 8,732 8,927 9,126Feasibility study, tender costs etc. 6,980 0 1,816 0 0 0 0 0 0 0 0 0 0 0 0Land expropriation 1,485 757 0 0 0 0 0 0 0 0 0 0 0 0 0Buildings 0 57,342 17,801 0 0 0 0 0 0 0 0 0 0 0 0Equipments 0 41,355 63,273 0 0 0 0 0 0 0 0 0 0 0 0Investments costs 8,465 99,454 82,889 0 0 0 0 0 0 0 0 0 0 0 0Replacement costs 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0Remediation and decontamination costs 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0Residual value 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0Other <strong>investment</strong> items 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0TOTAL INVESTMENT <strong>COST</strong>S 8,465 99,454 82,889 0 0 0 0 0 0 0 0 0 0 0 0TOTAL OUTFLOWS 8,465 99,454 82,889 4,511 7,322 7,485 7,651 7,821 7,995 8,173 8,355 8,541 8,732 8,927 9,126NET CASH FLOW -8,465 -99,454 -82,889 3,184 8,433 8,644 8,861 9,083 9,311 9,546 9,786 10,033 10,286 10,547 10,81416 17 18 19 20 21 22 23 24 25 26 27 28 29 30Municipal waste 4,105 4,166 4,228 4,291 4,355 4,420 4,486 4,553 4,621 4,690 4,759 4,830 4,902 4,975 5,049Other waste 308 313 317 322 327 332 336 342 347 352 357 362 368 373 379Electricity 10,126 10,390 10,662 10,940 11,226 11,519 11,820 12,129 12,446 12,771 13,104 13,447 13,798 14,158 14,528Heat 5,879 6,038 6,202 6,371 6,544 6,721 6,904 7,091 7,283 7,481 7,684 7,893 8,107 8,327 8,553SALES 20,418 20,907 21,409 21,924 22,451 22,992 23,546 24,114 24,696 25,293 25,905 26,532 27,175 27,833 28,509Labour cost 2,496 2,559 2,622 2,687 2,754 2,823 2,893 2,965 3,039 3,115 3,192 3,272 3,354 3,436 3,523Gas 303 312 322 332 342 353 364 375 387 399 411 424 438 451 465Eectrical energy 680 700 720 741 763 785 808 831 856 881 906 933 960 988 1,017Water services 9 9 9 10 10 10 10 11 11 11 11 12 12 12 13Raw material 357 364 371 379 386 394 402 410 418 427 435 444 453 462 471Intermediate services and goods 1,783 1,819 1,855 1,892 1,930 1,969 2,008 2,048 2,089 2,131 2,174 2,217 2,262 2,307 2,353Elimination <strong>of</strong> ash and slag waste 3,702 3,777 3,852 3,929 4,008 4,088 4,170 4,253 4,338 4,425 4,513 4,604 4,696 4,790 4,885TOTAL OPERATING <strong>COST</strong>S 9,330 9,539 9,752 9,970 10,193 10,421 10,655 10,894 11,138 11,388 11,644 11,905 12,173 12,446 12,727Feasibility study, tender costs etc. 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0Land expropriation 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0Buildings 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0Equipments 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0Investments costs 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0Replacement costs 0 0 0 72,383 0 0 0 0 0 0 0 0 0 0 0Remediation and decontamination costs 0 0 0 0 0 0 0 0 0 0 0 0 0 0 32,967Residual value 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -8,990Other <strong>investment</strong> items 0 0 0 72,383 0 0 0 0 0 0 0 0 0 0 23,977TOTAL INVESTMENT <strong>COST</strong>S 0 0 0 72,383 0 0 0 0 0 0 0 0 0 0 23,977TOTAL OUTFLOWS 9,330 9,539 9,752 82,353 10,193 10,421 10,655 10,894 11,138 11,388 11,644 11,905 12,173 12,446 36,704NET CASH FLOW 11,088 11,369 11,658 -60,429 12,258 12,570 12,891 13,220 13,558 13,905 14,261 14,627 15,002 15,388 -8,195Discount Rate 5.0%FNPV (C) -71,877.4FRR (C) 0.7%Funding Gap Ratio 0.42163
- Page 3:
ACRONYMS AND ABBREVIATIONSBAUB/CCBA
- Page 7 and 8:
TABLESTable 2.1 Financial analysis
- Page 9:
FIGURESFigure 1.1 Project cost spre
- Page 12 and 13:
Cohesion Fund, and through the leve
- Page 14 and 15:
or the plant will not reveal excess
- Page 17 and 18:
CHAPTER ONEPROJECT APPRAISAL IN THE
- Page 19 and 20:
Some specifications for financial t
- Page 21 and 22:
FOCUS: INFORMATION REQUIREDGeneral
- Page 23 and 24:
In particular, CBA results should p
- Page 25 and 26:
CHAPTER TWOAN AGENDA FOR THE PROJEC
- Page 27 and 28:
objectives, are, as far as possible
- Page 29 and 30:
considered the appropriate shadow p
- Page 31 and 32:
2.3.2 Feasibility analysisFeasibili
- Page 34 and 35:
This approach will be presented in
- Page 36 and 37:
Current assets include:- receivable
- Page 38 and 39:
The following items are usually not
- Page 40 and 41:
Mainly, the examiner uses the FRR(C
- Page 42 and 43:
The dynamics of the incoming flows
- Page 44 and 45:
eturn on their own capital (Kp). Th
- Page 46 and 47:
While the approach presented in thi
- Page 48 and 49:
2.5.1 Conversion of market to accou
- Page 50 and 51:
Table 2.9 Electricity price dispers
- Page 52 and 53:
2.5.1.2 Fiscal correctionsSome item
- Page 54 and 55:
previously estimated in projects wi
- Page 56 and 57:
FOCUS: ENPV VS. FNPVThe difference
- Page 58 and 59:
2.6 Risk assessmentProject appraisa
- Page 60 and 61:
Table 2.14 Impact analysis of criti
- Page 62 and 63:
Figure 2.6 Probability distribution
- Page 64 and 65:
eneficiary. The project proposer sh
- Page 66 and 67:
There are many ways to design an MC
- Page 68 and 69:
PROJECT APPRAISAL CHECK-LISTCONTEXT
- Page 70 and 71:
- reduction of congestion by elimin
- Page 72 and 73:
- the methods applied to estimate e
- Page 74 and 75:
- the marginal external costs: cong
- Page 76 and 77:
- the benefits for the existing tra
- Page 78 and 79:
The following tables show some refe
- Page 80 and 81:
3.1.1.6 Risk assessmentDue to their
- Page 82 and 83:
As shown in Figure 3.1, only under
- Page 84 and 85:
3.1.3.7 Other project evaluation ap
- Page 87 and 88:
- Waste Management Hierarchy rules
- Page 89 and 90:
The time horizon for a project anal
- Page 91 and 92:
3.2.1.7 Other project evaluation ap
- Page 93 and 94:
every user support the total costs
- Page 95 and 96:
Territorial reference frameworkIf t
- Page 97 and 98:
Cycle and phases of the projectGrea
- Page 99 and 100:
One of the most important aims of t
- Page 101 and 102:
projects, as in other sectors in wh
- Page 103 and 104:
3.2.3.2 Project identificationBasic
- Page 105 and 106:
3.2.3.7 Other project evaluation ap
- Page 107 and 108:
In order to evaluate the overall im
- Page 109 and 110:
for regassification plants, number
- Page 111 and 112: Examples of objectives are:- change
- Page 113 and 114: decontamination if any;- the techni
- Page 115 and 116: 3.3.3.6 Risk AnalysisCritical facto
- Page 117 and 118: 3.3.4.6 Risk assessmentCritical fac
- Page 119 and 120: 3.4.1.5 Economic analysisThe follow
- Page 121 and 122: Financial inflows• Admission fees
- Page 123 and 124: expectancy suitably adjusted by the
- Page 125 and 126: The time horizon for project analys
- Page 127 and 128: A Cost-Benefit Analysis should cons
- Page 129 and 130: CHAPTER FOURCASE STUDIESOverviewThi
- Page 131 and 132: - finally, there is the traffic tha
- Page 134 and 135: c) Road users producer’s surplus:
- Page 136 and 137: 4.1.5 Scenario analysisTwo scenario
- Page 138 and 139: The financial performance indicator
- Page 140 and 141: Table 4.10 Economic analysis (Milli
- Page 142 and 143: Table 4.12 Financial return on capi
- Page 144 and 145: 4.2 Case Study: investment in a rai
- Page 146 and 147: 4.2.4 Economic analysisThe benefits
- Page 148 and 149: Financial investment costs have bee
- Page 150 and 151: Figure 4.6 Results of the risk anal
- Page 152 and 153: Table 4.22 Economic analysis (Milli
- Page 154 and 155: Table 4.24 Financial return on capi
- Page 156 and 157: 4.3 Case Study: investment in an in
- Page 158 and 159: ate of 0.6% per year is assumed for
- Page 160 and 161: The shadow price of the CO 2 avoide
- Page 164 and 165: Table 4.36 Financial return on capi
- Page 166 and 167: 16 17 18 19 20 21 22 23 24 25 26 27
- Page 168 and 169: 4.4 Case Study: investment in a was
- Page 170 and 171: 4.4.2 Financial analysisAlthough in
- Page 172 and 173: THE CALCULATION OF REVENUESReferrin
- Page 174 and 175: 0.15 m 3 /m 2 a depreciation of 20%
- Page 176 and 177: As result, the probability distribu
- Page 178 and 179: Figure 4.13 Probability distributio
- Page 180 and 181: Table 4.48 Financial return on nati
- Page 182 and 183: Table 4.50 Financial return on priv
- Page 184 and 185: 16 17 18 19 20 21 22 23 24 25 26 27
- Page 186 and 187: 4.5 Case Study: industrial investme
- Page 188 and 189: 4.5.4.1 Investment costsThe total i
- Page 190 and 191: Finally, a residual value was estim
- Page 192 and 193: This analysis shows the need to pay
- Page 194 and 195: Table 4.62 Financial return on inve
- Page 196 and 197: Table 4.64 Return on private equity
- Page 198 and 199: Table 4.66 Economic analysis (thous
- Page 200 and 201: ANNEX ADEMAND ANALYSISDemand foreca
- Page 202 and 203: The method applied for the forecast
- Page 204 and 205: Furthermore, travel demand depends
- Page 206 and 207: This Guide supports a unique refere
- Page 208 and 209: A higher discount rate for countrie
- Page 210 and 211: Figure C.1 Project ranking by NPV v
- Page 212 and 213:
The main problems with this indicat
- Page 214 and 215:
EXAMPLE OF SHADOW WAGE IN DUAL MARK
- Page 216 and 217:
Another exhaustive way to include d
- Page 218 and 219:
Figure E.2 Percentage of low income
- Page 220 and 221:
ANNEX FEVALUATION OF HEALTH &ENVIRO
- Page 222 and 223:
Figure F.1 Main evaluation methodsS
- Page 224 and 225:
- expenditure on capital equipment
- Page 226 and 227:
due to air pollution or water conta
- Page 228 and 229:
BENEFIT TRANSFER - SELECTED REFEREN
- Page 230 and 231:
ANNEX GEVALUATION OF PPP PROJECTSIt
- Page 232 and 233:
adjustments for Competitive Neutral
- Page 234 and 235:
ANNEX HRISK ASSESSMENTIn ex-ante pr
- Page 236 and 237:
Reference ForecastingThe question o
- Page 238 and 239:
Figure H.5 Levels of risks in diffe
- Page 240 and 241:
ANNEX IDETERMINATION OF THE EU GRAN
- Page 242 and 243:
A.4. Technological Alternatives and
- Page 244 and 245:
GLOSSARYAccounting period: the inte
- Page 246 and 247:
Market price: the price at which a
- Page 248 and 249:
BIBLIOGRAPHY1. ReferencesBelli, P.,
- Page 250 and 251:
Ray, A. 1984, Cost-benefit analysis
- Page 252 and 253:
EnvironmentGeneralAtkinson, G., 200
- Page 254 and 255:
European Commission, DG Tren, 2003,