13.07.2015 Views

Guide to COST-BENEFIT ANALYSIS of investment projects - Ramiri

Guide to COST-BENEFIT ANALYSIS of investment projects - Ramiri

Guide to COST-BENEFIT ANALYSIS of investment projects - Ramiri

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

A simplified CBA usually implies focusing only on the key financial and economic tables (see below), withrough estimates <strong>of</strong> the data, because in a differential approach the absolute values <strong>of</strong> the variablesinvolved are less important than in a fully developed comparison <strong>of</strong> alternatives.The calculation <strong>of</strong> the financial and economic performance indica<strong>to</strong>rs must be made with the incrementalnet benefits technique, which considers the differences in the costs and benefits between the dosomethingalternative(s) and a single counterfactual without the project, that is, in principle, the BAUscenario.Under some exceptional circumstances, the BAU option should be disregarded and the do-minimumscenario used as the reference solution. In fact, in some cases, the BAU (do-nothing) scenario cannot beconsidered acceptable because it produces ‘catastrophic’ effects (see example below).EXAMPLE: CATASTROPHIC DO-NOTHING SCENARIOIt is cus<strong>to</strong>mary in project appraisal practice <strong>to</strong> consider at least three options: do-nothing (BAU), do-minimum and dosomething.In some cases the first option may produce ‘catastrophic’ effects so that it has <strong>to</strong> be neglected and the do-minimumbe considered as the baseline scenario.In the case <strong>of</strong> an outdated healthcare infrastructure, for example a hospital, which can no longer operate without renovation,BAU would mean the interruption <strong>of</strong> the service, which may be not acceptable <strong>to</strong> the Government. The baseline scenarioshould be that <strong>of</strong> renovating the infrastructure at least in a way <strong>to</strong> guarantee a minimum service. In practice, the catastrophic donothingoption leads us <strong>to</strong> consider the partial re<strong>investment</strong>s <strong>of</strong> the do-minimum option as the technically minimum capitalexpenditure <strong>to</strong> maintain the existing service. Again, there may be better do-something solutions, e.g. a new large infrastructureelsewhere, or a network <strong>of</strong> smaller clinics.One issue that sometimes arises when considering the expansion or restructuring <strong>of</strong> existing <strong>projects</strong> ishow <strong>to</strong> ‘apportion’ incremental flows between the old and the new capacity. Unfortunately, simpleaccounting apportionment rules (e.g. the share <strong>of</strong> ‘old’ and ‘new’ revenues are attributed in proportion <strong>to</strong>‘old’ and ‘new’ capital expenditures) are <strong>of</strong>ten misleading. The right approach is always <strong>to</strong> compare the‘with’ and ‘without’ project scenarios, albeit in a sketchy way. Thus, the incremental revenues or timesaving benefits <strong>of</strong> the third lane in an existing <strong>to</strong>lled two-lane highway must be related <strong>to</strong> a forecast <strong>of</strong>incremental traffic and cannot be assumed <strong>to</strong> be one third <strong>of</strong> the future traffic.In other cases, again for <strong>projects</strong> consisting <strong>of</strong> upgrading or extension <strong>of</strong> a previous infrastructure, anincremental benefit cannot always be quantified in terms <strong>of</strong> output, because the output does not change atall. In such cases, the incremental benefit should <strong>of</strong>ten be appraised as an improvement, for example, inservice quality, or as avoided cost, because <strong>of</strong> service interruptions (e.g. based on willingness-<strong>to</strong>-pay forquality or continuity <strong>of</strong> supply <strong>of</strong> electricity).EXAMPLE: OPTION <strong>ANALYSIS</strong> OF THE WATERWAY CROSSING MAGDEBURG PROJECT (GERMANY)The Waterway Crossing Magdeburg is part <strong>of</strong> the German midland canal which crosses the centre <strong>of</strong> Germany from West <strong>to</strong>East, namely from the Ruhr area <strong>to</strong> Berlin. It consists <strong>of</strong> a 918 m. channel bridge above the Elbe river and it is owned andmanaged by the Federal German Waterway and Navy Agency.During the ex-ante project appraisal, three different do-something alternatives were considered in the options analysis:- one-way bridge (no parallel usage possible – alternative 1),- two-way bridge (bridge can be used in both directions at the same time – alternative 2),- dam alternative (independence <strong>of</strong> the water level <strong>of</strong> the river Elbe – alternative 3).The alternatives were analysed with the CBA methodology and were compared with a ‘do-minimum’ scenario, because somere<strong>investment</strong>s on the existing infrastructure would have been necessary even without the implementation <strong>of</strong> any additionalproject.All analysed alternatives achieved very good economic results, but the ‘one-way bridge’ across the river Elbe showed the bestBenefit/Cost ratio and was therefore the option implemented.Source: EVA-TREN2.4 Financial analysisThe main purpose <strong>of</strong> the financial analysis is <strong>to</strong> use the project cash flow forecasts <strong>to</strong> calculate suitable netreturn indica<strong>to</strong>rs. In this <strong>Guide</strong> a particular emphasis is placed on two financial indica<strong>to</strong>rs: the FinancialNet Present Value (FNPV) and the Financial Internal Rate <strong>of</strong> Return (FRR), respectively in terms <strong>of</strong>return on the <strong>investment</strong> cost, FNPV(C) and FRR(C), and return on national capital, FNPV(K) andFRR(K).32

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!