13.07.2015 Views

Guide to COST-BENEFIT ANALYSIS of investment projects - Ramiri

Guide to COST-BENEFIT ANALYSIS of investment projects - Ramiri

Guide to COST-BENEFIT ANALYSIS of investment projects - Ramiri

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Figure 2.6 Probability distribution for NPV0.160.14Probablity distribution0.120.10.080.060.040.020-10 -5 -4 -2 0 2 4 8 12 15 18 20NPVThe cumulative probability curve (or a table <strong>of</strong> values) permits an assessement <strong>of</strong> the project risk, forexample by verifying whether the cumulative probability is higher or lower than a reference value that isconsidered <strong>to</strong> be critical. One can also assess the probability that the NPV (or FRR) will be lower than acertain value, which is adopted as the benchmark (e.g. zero for NPV and 5% for FRR). In the example,see Figure 2.7, there is a probability <strong>of</strong> about 30% that the NPV will be negative.Figure 2.7 Cumulative probability distribution for NPV120%Cumulative Probability100%80%60%40%20%0%-10 -5 -4 -2 0 2 4 8 12 15 18 20NPV2.6.4 Assessment <strong>of</strong> acceptable levels <strong>of</strong> riskOften the NPVs and IRRs reported in project appraisal reports refer <strong>to</strong> best or baseline estimates, perhapsmeaning ‘most likely’ values (or mode). However, the criterion for project acceptability should be that <strong>of</strong>the expected value (or mean) <strong>of</strong> such indica<strong>to</strong>rs, calculated from the underlying probability distributions.For instance, if a project has an ERR <strong>of</strong> 10% but also the probability risk analysis tells us that the ERR hasa value between 4 and 10 with a probability <strong>of</strong> 70% and a value between 10 and 13 with a probability <strong>of</strong>30%, then the expected value <strong>of</strong> ERR for that project is only 8.35% [average(4,10)*0.7 +average(10,13)*0.3].In conclusion, the procedure described allows for the selection <strong>of</strong> <strong>projects</strong> not only on the basis <strong>of</strong> thebest estimate, but also based on the risk associated with it, simply by weighting the performance with therisk. In principle, the expected performance, and not the modal one, is the value that should be reportedin the application form for major <strong>projects</strong> requiring EU assistance. In order <strong>to</strong> evaluate the result, one62

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!