28.11.2012 Views

Newlands Cross Upgrade EIS - European Investment Bank

Newlands Cross Upgrade EIS - European Investment Bank

Newlands Cross Upgrade EIS - European Investment Bank

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

South Dublin County Council N7 <strong>Newlands</strong> <strong>Cross</strong> <strong>Upgrade</strong><br />

Environmental Impact Statement<br />

Arup Consulting Engineers<br />

These figures are out-turn costs and exclude risk items, fees and land acquisition costs.<br />

The following assumptions have been made in developing the construction costs:<br />

• Construction will commence in early 2009 and take up to two years for the overpass and<br />

up to three years for the underpass<br />

• The procurement method for the works will be Design and Build<br />

• No lane rental costs have been included<br />

• No special phasing requirements have been included<br />

• The costs include for construction inflation of 4% per annum until early 2009 and 5% per<br />

annum thereafter<br />

• The costs include the costs of all temporary traffic management<br />

It should be noted that the construction costs presented here represent the main cost difference<br />

between the two options. The permanent and temporary land costs are assumed to be equal as<br />

the landtake is assumed to be the same, even though in the case of the Underpass option, the<br />

temporary land will be required for a longer period.<br />

The principal reasons for the difference in construction costs between the options are:<br />

• The underpass includes for the excavation of a significant quantity of competent limestone<br />

bedrock<br />

• The cost of the retaining structures required for the Underpass is significantly greater that<br />

the cost of those required for the Overpass.<br />

• The cost of the pavement for the Underpass includes a concrete base slab to resist<br />

groundwater pressures<br />

• The longer construction duration of the Underpass option increases the Conractor’s<br />

Preliminaries costs<br />

3.15 Conclusions and Recommendations<br />

In this report we considered two proposed options i.e. Underpass and Overpass, in the context<br />

of their respective construction and operational impacts. A summary of the impacts is<br />

presented in the Options Matrix (See Figures 3.11a – 3.11c).<br />

In summary however, our examination of both options revealed the following issues.<br />

Firstly, there are significant construction issues with the Underpass Option when compared<br />

with the Overpass Option. To construct the Underpass, approximately 6 metres of rock would<br />

need to be excavated, which given the location of the junction, would be a time consuming<br />

and onerous task. As a result of this issue construction of the underpass could take<br />

approximately 1 year longer. This increased duration in turn has a number of knock on effects<br />

with regard to traffic disruption, severance, noise and dust. On a national road of such<br />

importance these issues equate to significant impacts.<br />

Conversely, the Overpass Option has greater operational impacts. Noise levels will increase<br />

slightly at approximately 5 No. receptors. However, this impact can be mitigated back to at<br />

least existing levels. There will also be an increased visual impact with the overpass option<br />

particularly at a number of residences along the northern boundary east of the junction, at<br />

Bewleys Hotel and at the Golf Club. These impacts can also be mitigated somewhat through a<br />

combination of materials selection and landscape design. Following mitigation, the impact<br />

will be moderate and neutral.<br />

December 2007 Page 65

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!