28.11.2012 Views

Newlands Cross Upgrade EIS - European Investment Bank

Newlands Cross Upgrade EIS - European Investment Bank

Newlands Cross Upgrade EIS - European Investment Bank

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

South Dublin County Council N7 <strong>Newlands</strong> <strong>Cross</strong> <strong>Upgrade</strong><br />

Environmental Impact Statement<br />

Arup Consulting Engineers<br />

Permanent ground anchors will be installed as excavation proceeds and construction of the<br />

permanent base slab will commence.<br />

The precast prestressed concrete beams for the bridge deck and the permanent GRC formwork<br />

panels will be placed and the reinforced concrete in-situ deck slab will be cast. The surfacing,<br />

parapets, drainage and other finishes for the underpass bridge deck will also be put in place.<br />

Stage 3: The Fonthill / Belgard Road (R113) through traffic will be diverted onto the<br />

completed eastern half of the bridge deck. Construction of the secant piled wall, which will<br />

form the sub-structure for the western half of the bridge deck, will commence.<br />

The precast beams of the bridge deck and the permanent formwork panels will be placed and<br />

the RC deck slab will be cast.<br />

Excavation for the underpass at the remote eastern and western ends of the project will<br />

continue. This excavation will be in open cut with RC retaining walls. Excavation within the<br />

vicinity of the secant piled walls will also continue and again will stop within a safe distance<br />

of the bridge structure. Permanent ground anchors will be installed as excavation proceeds and<br />

construction of the permanent base slab will commence.<br />

The surfacing, parapets, drainage and other finishes for the remainder of the underpass bridge<br />

deck will also be put in place.<br />

Stage 4: Excavation of the underpass beneath and immediately either side of the bridge deck<br />

will commence with ground anchors installed where appropriate as the excavation proceeds.<br />

The base slab to the underpass as well as the road pavement, drainage, safety barriers, and<br />

lighting will be constructed. Fascia panels and other finishes to the carriageway will be<br />

installed.<br />

Stage 5: Eastbound and westbound traffic will be diverted back onto the re-aligned Naas<br />

Road (N7) to provide free flowing traffic beneath the junction. Contra flow operations on the<br />

bridge deck will also be removed when the bridge deck is complete.<br />

Stage 6: The westbound diversion to the south of the underpass will be removed and the final<br />

highway arrangement for the westbound merge and diverge lanes will be completed. The<br />

highway arrangements to the north of the underpass structure will be completed in phases to<br />

facilitate traffic movements.<br />

Stage 7: All remaining highway upgrade works will be completed in stages to the Fonthill<br />

Road, Belgard Road and to the at-grade junction on the bridge deck. All landscaping, lighting<br />

and drainage elements will also be finalised at this time.<br />

3.7.3 Construction Duration<br />

It is estimated that the construction of the Overpass could take up to 2 years.<br />

However, the Underpass Option could take up to 3 years to construct as it would involve<br />

removing a significant quantity of rock to allow the mainline N7 to be placed under the<br />

Fonthill/Belgard Road (R113).<br />

3.7.4 Construction Traffic<br />

It is estimated that at its busiest there will be approximately 20 HGV vehicles per hour<br />

arriving at the site (worst case scenario) for the overpass scheme. The underpass will generate<br />

a greater number of additional movements resulting from the excavation of the rock and the<br />

piling activities.<br />

The speed limit on the temporary road layout during construction will be 60 km/hr during<br />

construction. It is likely that there will be 2 No. entry and 2 No. exit points for construction<br />

traffic in both directions. For the eastbound approach into Dublin it is estimated that there will<br />

December 2007 Page 22

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!