28.11.2012 Views

Newlands Cross Upgrade EIS - European Investment Bank

Newlands Cross Upgrade EIS - European Investment Bank

Newlands Cross Upgrade EIS - European Investment Bank

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

South Dublin County Council N7 <strong>Newlands</strong> <strong>Cross</strong> <strong>Upgrade</strong><br />

Environmental Impact Statement<br />

Arup Consulting Engineers<br />

Many of the items listed above are similar to both of the proposed schemes and therefore are<br />

not discussed in this report. Those issues which are not similiar to both schemes are addressed<br />

in the following sections.<br />

3.7.2 Construction Methodology<br />

The following sections describe how both of these options would be constructed.<br />

3.7.2.1 Option 1 – Overpass<br />

The Overpass option would be constructed in seven stages as follows as depicted in Figures<br />

4.10 – 4.16 inclusive:<br />

Stage 1: Temporary traffic diversions will be constructed offline and to the south of the<br />

proposed overbridge location. This will include the construction of as much of the permanent<br />

works as is feasible. The temporary diversions will facilitate the diversion of the Naas Road<br />

(N7) from its current alignment and enable construction works to commence to the north of<br />

the scheme. Temporary traffic lights and road markings will also be installed for traffic<br />

management purposes at this time.<br />

Stage 2: The abutment walls and the bridge piers in the central island will be constructed.<br />

Reinforced soil approach embankments will also be constructed at this time.<br />

Stage 3: Precast beams will be lifted into place during a series of overnight road closures.<br />

Glass fibre reinforced concrete permanent formwork will be placed between precast beams, to<br />

enable the construction of the deck slab to proceed above the live traffic on the<br />

Fonthill/Belgard Road (R113) beneath.<br />

Stage 4: The Reinforced Concrete deck slab and parapet edge beams will be cast. Deck<br />

surfacing, lighting and drainage will be added to the overbridge structure<br />

The road pavement on the approach embankments will be constructed together with the<br />

drainage, lighting, noise barriers (where required) and central reserve vertical concrete barrier.<br />

Stage 5: Traffic will be redirected onto the overbridge structure. The temporary westbound<br />

diversion to the south of the overbridge will be removed and the final highway arrangement<br />

for the westbound merge and diverge lanes will be constructed. The highway arrangement to<br />

the north of the overbridge structure will also be constructed.<br />

Stage 6: All remaining highway upgrade works will be completed including the landscaping,<br />

lighting and drainage elements.<br />

Stage 7: Final Highway Scheme Arrangement<br />

3.7.2.2 Option 2 – Underpass<br />

This Underpass would be constructed in seven stages as follows:<br />

Stage 1: Construct the temporary road diversion to the south of the underpass to facilitate the<br />

temporary diversions of the eastbound and westbound carriageways. Traffic management<br />

measures will also be addressed at this time.<br />

Stage 2: Construct a Secant Piled Wall to the underpass. The bridge deck to carry the<br />

Fonthill/Belgard Road (R113) over the underpass is to be built in two stages and the<br />

excavation is to use the top-down construction method.<br />

Excavation for the underpass will commence at the remote eastern and western ends of the<br />

project. At these locations the underpass will be constructed in open cut and utilise reinforced<br />

concrete retaining walls. As much of the excavation as possible will take place within the<br />

vicinity of the Secant Piled Walls but stopping within a safe distance of the bridge structure.<br />

December 2007 Page 21

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!