South Dublin County Council N7 <strong>Newlands</strong> <strong>Cross</strong> <strong>Upgrade</strong><br />
Environmental Impact Statement<br />
Arup Consulting Engineers<br />
be an entry point at the most western point of the works with an exit just before <strong>Newlands</strong><br />
<strong>Cross</strong> Junction.<br />
The second entry point will be the other side of the junction with an exit close to the most<br />
easterly point of the works. There will be a similiar arrangement for traffic coming from<br />
Dublin travelling westbound i.e. the first entry close to the most easterly point of the works,<br />
exiting in advance of the junction and the second entry just beyond the junction, exiting at the<br />
western most point of the works.<br />
3.7.5 Traffic Management during Construction<br />
A number of traffic management measures will be implemented during the phasing of<br />
construction works for both options as follows.<br />
3.7.5.1 Option 1 – Overpass<br />
Temporary traffic diversions will be constructed offline and to the south of the proposed<br />
overbridge location to facilitate the diversion of the Naas Road (N7) from its current<br />
alignment while existing traffic flow is maintained. Temporary traffic lights, barriers and road<br />
markings will also be put in place. All existing traffic movements will be accommodated<br />
within the temporary traffic phasing.<br />
There will be a number of overnight closures when the precast beams are being lifted into<br />
place. These closures will occur to the east and west spans of the bridge deck. Traffic,<br />
pedestrian and cycle movement through the junction will be facilitated during this period.<br />
Once constructed all mainline N7 traffic will be diverted onto the overbridge structure. The<br />
temporary diversions will be removed and final highway arrangements for the merge and<br />
diverge lanes will be constructed in stages to facilitate relevant left, right and through turning<br />
movements. Left, right and through turning movements will also be accommodated while<br />
remaining upgrade works are carried out on the Fonthill / Belgard Road (R113).<br />
Traffic management during construction is depicted on Figure 3.5a and 3.5b.<br />
3.7.5.2 Option 2 – Underpass<br />
Initially, traffic flow will be maintained through the junction as per the existing layout while<br />
offline works such as temporary traffic barriers, site compounds, temporary road diversions<br />
for eastbound and westbound carriageways and utilities, road markings and temporary traffic<br />
lights are put in place.<br />
While the underpass is being constructed mainline traffic will be diverted to the north and<br />
south of the proposed N7 mainline. The Fonthill / Belgard Road (R113) traffic will be<br />
diverted through the junction using a contraflow system. The traffic will be diverted in two<br />
stages to facilitate construction of the bridge in two halves. Once the eastern half of the bridge<br />
deck carrying the Fonthill / Belgard Road (R113) over the N7 mainline is complete then the<br />
Fonthill / Belgard Road (R113) traffic will be diverted onto that portion of the completed<br />
bridge in order that the western half of the bridge can be constructed.<br />
Once the bridge deck is complete the contraflow system on the Fonthill / Belgard Road<br />
(R113) will be removed. The traffic will also be diverted back onto the Naas Road (N7)<br />
following completion of the re-alignment. The temporary diversions will be removed and<br />
final highway arrangements for the merge and diverge lanes will be constructed in stages to<br />
facilitate relevant left, right and through turning movements. Left, right and through turning<br />
movements will also be accommodated while remaining upgrade works are carried out on the<br />
Fonthill / Belgard Road (R113).<br />
Traffic management for the N7 mainline during construction of the Underpass is depicted on<br />
Figure 3.5c, 3.5d, 3.5e and 3.5f.<br />
December 2007 Page 23